Last business day of January 2025 · Target: Jan 31, 2025
✗ SLA Missed (222 biz days late)
Active: 243 biz days
Paused: 97 biz days
🕐 Clock stopped: Completed (May 13, 2026)
236d
▶ Clock Running
Status: Created
Jan 2 → Dec 12, 2025
236 business days (counted)
Running total: 236 of ? biz days used
⏸76d
⏸ Clock Paused
Status: Ready for Release
Dec 12 → Apr 3, 2026
76 business days (not counted)
▶ Clock Running
Status: Scheduled
Apr 3 → Apr 8, 2026
3 business days (counted)
Running total: 239 of ? biz days used
▶ Clock Running
Status: Entered
Apr 8 → Apr 8, 2026
0 business days (counted)
Running total: 239 of ? biz days used
⏸ Clock Paused
Status: Ready for Release
Apr 8 → Apr 10, 2026
2 business days (not counted)
▶ Clock Running
Status: Scheduled
Apr 10 → Apr 15, 2026
3 business days (counted)
Running total: 242 of ? biz days used
▶ Clock Running
Status: Entered
Apr 15 → Apr 15, 2026
0 business days (counted)
Running total: 242 of ? biz days used
⏸ Clock Paused
Status: Ready for Release
Apr 15 → May 12, 2026
19 business days (not counted)
▶ Clock Running
Status: Scheduled
May 12 → May 13, 2026
1 business day (counted)
Running total: 243 of ? biz days used
▶ Clock Running
Status: Tech On Site
May 13 → May 13, 2026
0 business days (counted)
Running total: 243 of ? biz days used
Created: Jan 2, 2025Completed: May 13, 2026
Show SLA Clock Detail (10 periods)
Period
Status
Clock
Biz Days
Running Total
Jan 2 → Dec 12
Created
▶ Running
236
236
Dec 12 → Apr 3
Ready for Release
⏸ Paused
76
—
Apr 3 → Apr 8
Scheduled
▶ Running
3
239
Apr 8 → Apr 8
Entered
▶ Running
0
239
Apr 8 → Apr 10
Ready for Release
⏸ Paused
2
—
Apr 10 → Apr 15
Scheduled
▶ Running
3
242
Apr 15 → Apr 15
Entered
▶ Running
0
242
Apr 15 → May 12
Ready for Release
⏸ Paused
19
—
May 12 → May 13
Scheduled
▶ Running
1
243
May 13 → May 13
Tech On Site
▶ Running
0
243
Holding335.8d (excluded)
Coordinators8.9d
Field Work0.1d
Billing14.0d
✗ SLA Missed
Holding(excluded from total)
335.8 days
Coordinators
8.9 days
Over SLA
Field Work
0.1 days
Billing
14.0 days
Over SLA
Created: Jan 2, 2025
Due: Dec 31, 2026
Completed: May 13, 2026 (232 days early)
📅
340.5 daysTotal Age
⏱️
236.5d in On HoldLongest Stage
🔄
12 transitionsStatus Changes
⚠️
17.4d overTotal Delay
📦
0 orders, 0 quotesParts & Quotes
📝
3 linesWork Details
🏠
1 visitOn-Site Trips
👤
Self-ScheduledScheduling
AI Analysis
Powered by OpenAI
Generating AI analysis...
Completed with significant delays
Invoiced • 588 days old
🚨
Primary Delay236.5 days stuck in "On Hold"
⏱️
Total Delay17.4 business days over SLA thresholds
SLA vs Actual Time by Status
Actual (within SLA)
Actual (over SLA)
SLA Target
On Hold
236.5d
Ready for Release
99.3d
Scheduled
8.9d / 2.0d SLA
Tech On Site
0.1d / 1.0d SLA
Completed
0.0d / 1.0d SLA
Closed
2.0d / 1.0d SLA
Ready to Bill
14.0d / 1.0d SLA
Invoice Pending
0.0d / 2.0d SLA
💬 Activities, Notes & Communications
🔒Internal CSA Notes
4/15/26 AJinerson - Tech unable to service yesterday. Clearing tech name and placing back into RFR.
4/8/26 AJinerson - Tech unable to service today. Clearing tech name and placing back into RFR.
🔧Work Performed
Completed p.m. service
🔍Technician Findings
Kiosk is operational
⚠️Problem Description
Please Perform PM: PM Checklist can be found as a link in the work order under WO actions
If Kiosk is not on the Sales floor request to speak to a manager to find out if kiosk is being stored in the back room or if it was disposed. Offer to help bring the kiosk to the salesfloor or advise that EMSAR can replace a disposed kiosk. If store does not want to bring the kiosk out of storage or if kiosk was disposed, close out work order with Repair code '37 Store intervention required' and document who you spoke with and outcome of conversation. Labor line shall be a trip charge.
***Important: Please make sure to document if kiosk is disposed or in storage***
If kiosk fails a PM, checklist is still required to be completed. Please use Code 35 - Follow up needed and detail in the Tech Findings, Work Performed and Final condition the result and cause for a follow up. Close out the work order. Dispatch will create a follow up repair work order to send parts.