Work Order 360 View
Detailed work order timeline, KPIs, and analysis
PC
SLA Clock
Per client agreement · Target: Dec 31, 2025
0 biz days remaining
▶ Clock Running
Status: Created
Feb 11 → Feb 11, 2025
0 business days (counted)
Running total: 0 of ? biz days used
46d
▶ Clock Running
Status: On Hold
Feb 11 → Apr 17, 2025
46 business days (counted)
Running total: 46 of ? biz days used
▶ Clock Running
Status: Ready for Scheduling
Apr 17 → May 23, 2025
26 business days (counted)
Running total: 72 of ? biz days used
⏸305d
⏸ Clock Paused
Status: Ready for Release
May 23 → Aug 15, 2026
305 business days (not counted)
Created: Feb 11, 2025
Today
Show SLA Clock Detail (4 periods)
| Period |
Status |
Clock |
Biz Days |
Running Total |
| Feb 11 → Feb 11 |
Created |
▶ Running
|
0 |
0 |
| Feb 11 → Apr 17 |
On Hold |
▶ Running
|
46 |
46 |
| Apr 17 → May 23 |
Ready for Scheduling |
▶ Running
|
26 |
72 |
| May 23 → Aug 15 |
Ready for Release |
⏸ Paused
|
305 |
—
|
Dispatch
1.0 days
Over SLA
Holding (excluded from total)
47.0 days
Coordinators
26.8 days
Over SLA
Created: Feb 11, 2025
Due: Dec 31, 2025 (227 days overdue)
⏱️
47.0d in On Hold
Longest Stage
🔄
3 transitions
Status Changes
⚠️
26.3d over
Total Delay
📦
0 orders, 0 quotes
Parts & Quotes
AI Analysis
Powered by OpenAI
Generating AI analysis...
🚨
Primary Delay
47.0 days stuck in "On Hold"
⏱️
Total Delay
26.3 business days over SLA thresholds
SLA vs Actual Time by Status
Ready for Scheduling
26.8d
/ 1.0d SLA
💬 Activities, Notes & Communications
🔒
Internal CSA Notes
02/06/2026 MHamersley - Planner & FOM working w/ POC to locate devices as they become available
12/17/2025 MHamersley - Working with Fady on update for visit #2, once devices are returned to customer.
10/29/2025 MKlose planner to get with Fady for update on visit #2.
06/12/2025 Cever waiting on devices to be returned to customer
Visit #2
⚠️
Problem Description
Visit #2 - Tempus LS Manual Pacing
📄
Description
Philips Healthcare Tempus ALS Defibrillator
📞
Call Description
FCO86700002
📧
Email_FCO Updates
Completed
Oct 29, 2025
10/29/2025 MKlose planner to get with Fady for update on visit #2.
Timeline
📋
Work Order:
WO-01246649
Type:
FCO
Priority:
PC
⏸️
From:
Entered
To:
On Hold
Duration in Previous:
10h 21m
📅
From:
On Hold
To:
Ready for Scheduling
Duration in Previous:
65d 3h
✅
From:
Ready for Scheduling
To:
Ready for Release
Duration in Previous:
36d 2h
Bottlenecks
Entered
Duration: 1.0 business days (threshold: 4.0 business hours)
Exceeded by 4.0 business hours
Ready for Scheduling
Duration: 26.8 business days (threshold: 1.0 business days)
Exceeded by 25.8 business days