📍 Mt Sinai Hospital — 101st St, New York NY, 10029
Aug 27, 2025 → May 14, 2026
✅ Completed
PC
SLA Clock
Per client agreement · Target: May 30, 2026
✓ SLA Met (10 biz days early)
Active: 17 biz days
Paused: 159 biz days
🕐 Clock stopped: Completed (May 14, 2026)
▶ Clock Running
Status: Created
Aug 28 → Aug 28, 2025
0 business days (counted)
Running total: 0 of ? biz days used
⏸159d
⏸ Clock Paused
Status: Ready for Release
Aug 28 → Apr 21, 2026
159 business days (not counted)
17d
▶ Clock Running
Status: Scheduled
Apr 21 → May 14, 2026
17 business days (counted)
Running total: 17 of ? biz days used
Created: Aug 28, 2025Completed: May 14, 2026
Show SLA Clock Detail (3 periods)
Period
Status
Clock
Biz Days
Running Total
Aug 28 → Aug 28
Created
▶ Running
0
0
Aug 28 → Apr 21
Ready for Release
⏸ Paused
159
—
Apr 21 → May 14
Scheduled
▶ Running
17
17
Dispatch0.9d
Holding160.0d (excluded)
Coordinators17.9d
Field Work0.0d
Billing1.3d
✓ SLA Met
Dispatch
0.9 days
Over SLA
Holding(excluded from total)
160.0 days
Coordinators
17.9 days
Over SLA
Field Work
0.0 days
Billing
1.3 days
Over SLA
Created: Aug 28, 2025
Due: May 30, 2026
Completed: May 14, 2026 (16 days early)
📅
177.0 daysTotal Age
⏱️
160.0d in Ready for ReleaseLongest Stage
🔄
7 transitionsStatus Changes
⚠️
16.7d overTotal Delay
📦
0 orders, 0 quotesParts & Quotes
📝
10 linesWork Details
🏠
2 visitsOn-Site Trips
📋
CoordinatorScheduling
🔄
2 On-Site Visits
2 on-site visits — follow-up trip required
Visit 1May 13, 2026
Visit 2May 14, 2026
AI Analysis
Powered by OpenAI
Generating AI analysis...
Completed with significant delays
Invoiced • 353 days old
🚨
Primary Delay160.0 days stuck in "Ready for Release"
⏱️
Total Delay16.7 business days over SLA thresholds
SLA vs Actual Time by Status
Actual (within SLA)
Actual (over SLA)
SLA Target
Entered
0.9d / 0.5d SLA
Ready for Release
160.0d
Scheduled
17.9d / 2.0d SLA
Completed
0.0d / 1.0d SLA
Closed
0.5d / 1.0d SLA
07e-Partial Project
0.3d
Ready to Bill
1.3d / 1.0d SLA
💬 Activities, Notes & Communications
🔒Internal CSA Notes
04/21/2026 DMalloy - Dispatched for FSE Andre to walk in on one day next week after 5PM.
04/09/2026 DMalloy - Emailed customer proposing FSE Vivian be on site on Saturday, 5/2/2026 at 9:00am.
juanita.jordan@mountsinai.org
02/06/2026 RArnold - Customer requests weekend scheduling and closer to the month due
01/29/2026 RArnold - Per email Juanita asked DSM if he knows what room device was installed in
01/23/2026 RArnold - emailed juanita.jordan@mountsinai.org see if this device is hers
🔧Work Performed
PERFORMED ANNUAL PREVENTIVE MAINTENANCE AND PERFORMANCE ASSURANCE TEST AND INSPECTION. ALL PM AND PA RESULTS PASSED.ADVISED CUSTOMER AND PLACED BACK INTO SERVICE.
🔍Technician Findings
PERFORMED ANNUAL PREVENTIVE MAINTENANCE AND PERFORMANCE ASSURANCE TEST AND INSPECTION. ALL PM AND PA RESULTS PASSED.ADVISED CUSTOMER AND PLACED BACK INTO SERVICE.
⚠️Problem Description
IntraSight Mobile - SN 100749 - IP 106841266
📄Description
Philips - Image Guided Therapy Device (IGT-D)
📞Call Description
PM - Contract - BG Required PM
📅
WO-01300028 - PM - DD: 5/30/2026 - - IGT-D - New York - Mt Sinai Hospital
May 5, 2026 5:00pm – 7:00pm
Work Order: WO-01300028
Account: PHILIPS HEALTHCARE
Customer Case Number: WO-12697959
Location: Mt Sinai Hospital
Address: 101st St, New York, NY 10029
Manufacturer: Philips
Model #: IGT-D
Serial #: IGT-D100749
Contact Name:
Contact Phone:
Contact Email:
Due Date: 5/30/2026
Scheduled
Timeline
📋
Work Order Created Aug 27, 11:09 PM
Work Order:WO-01300028
Type:PM
Priority:PC
✅
Status: Ready for Release by Mandy NewmanAug 28, 6:19 AM