📍 Hunterdon Medical Center — 2100 Wescott Dr, Flemington NJ, 08822
Sep 5, 2025 → Jul 2, 2026
✅ Completed
PC
SLA Clock
Per client agreement · Target: Aug 30, 2026
✓ SLA Met (40 biz days early)
Active: 44 biz days
Paused: 160 biz days
🕐 Clock stopped: Completed (Jul 3, 2026)
▶ Clock Running
Status: Created
Sep 5 → Sep 5, 2025
0 business days (counted)
Running total: 0 of ? biz days used
⏸160d
⏸ Clock Paused
Status: Ready for Release
Sep 5 → Apr 29, 2026
160 business days (not counted)
▶ Clock Running
Status: Assigned
Apr 29 → Apr 29, 2026
0 business days (counted)
Running total: 0 of ? biz days used
44d
▶ Clock Running
Status: Scheduled
Apr 29 → Jul 3, 2026
44 business days (counted)
Running total: 44 of ? biz days used
Created: Sep 5, 2025Completed: Jul 3, 2026
Show SLA Clock Detail (4 periods)
Period
Status
Clock
Biz Days
Running Total
Sep 5 → Sep 5
Created
▶ Running
0
0
Sep 5 → Apr 29
Ready for Release
⏸ Paused
160
—
Apr 29 → Apr 29
Assigned
▶ Running
0
0
Apr 29 → Jul 3
Scheduled
▶ Running
44
44
Dispatch0.0d
Holding160.3d (excluded)
Coordinators44.7d
Billing1.5d
✓ SLA Met
Dispatch
0.0 days
Holding(excluded from total)
160.3 days
Coordinators
44.7 days
Over SLA
Billing
1.5 days
Over SLA
Created: Sep 5, 2025
Due: Aug 30, 2026
Completed: Jul 3, 2026 (58 days early)
📅
204.4 daysTotal Age
⏱️
160.3d in Ready for ReleaseLongest Stage
🔄
7 transitionsStatus Changes
⚠️
43.7d overTotal Delay
📦
0 orders, 0 quotesParts & Quotes
📝
4 linesWork Details
🏠
1 visitOn-Site Trips
📋
CoordinatorScheduling
AI Analysis
Powered by OpenAI
Generating AI analysis...
Completed with significant delays
Invoiced • 343 days old
🚨
Primary Delay160.3 days stuck in "Ready for Release"
⏱️
Total Delay43.7 business days over SLA thresholds
SLA vs Actual Time by Status
Actual (within SLA)
Actual (over SLA)
SLA Target
Entered
0.0d / 0.5d SLA
Ready for Release
160.3d
Assigned
0.6d / 0.5d SLA
Scheduled
44.1d / 2.0d SLA
Closed
2.0d / 1.0d SLA
07e-Partial Project
3.0d
Ready to Bill
1.5d / 1.0d SLA
💬 Activities, Notes & Communications
🔒Internal CSA Notes
06/25/2026 MKlose- POC confirm July 2 at 10am
06/25/2026 MKlose- sent email to see if Phil could complete July 2nd or week of 13th
04/29/2026 mklose rcvd email from Michael adv Phil on site July 8th
04/28/2026 YEspino Called 908-788-6117 to speak to anthony over the pm in question. Was able to speak to Anthony and he advised he is trying to confirm that this device is still oniste and scheduling with the dept. He advised he would reply via email with an update.
04/20/2026 mklose sent 1st attempt email to Anthony Celambrino <acelambrino@hhsnj.org>; Hubner, Michael <michael.hubner@philips.com>
🔧Work Performed
PM Transducer, X8-2t - IP 101408556 - SN F07KQV
🔍Technician Findings
PM Transducer, X8-2t - IP 101408556 - SN F07KQV
⚠️Problem Description
Transducer, X8-2t - IP 101408556 - SN F07KQV
📞Call Description
PM - Contract - BG Required PM
📋
0-0-0
Completed Jul 7, 2026
Tech Supervisor Spot Check
# of Critical Defects: 0
# of Major Defects: 0
# of Minor Defects: 0
# of EMSAR Defects: 0
Ultrasound - PM
a. Tools : Electrical Safety & Phantom – YES
b. Prontoforms – uploaded and correct template – YES
c. CSR – signed and uploaded to ServiceMax - YES
📞
Live Call_ Left Message
Completed Apr 28, 2026
04/28/2026 YEspino Called 908-788-6117 to speak to anthony over the pm in question. Was able to speak to Anthony and he advised he is trying to confirm that this device is still oniste and scheduling with the dept. He advised he would reply via email with an update.
📅
WO-01302210 - PM - DD: 8/30/2026 - - Ultrasound - Flemington - Hunterdon Medical Center
Jul 2, 2026 10:00am – 12:00pm
Work Order: WO-01302210
Account: PHILIPS HEALTHCARE
Customer Case Number: WO-13254504
Location: Hunterdon Medical Center
Address: 2100 Wescott Dr, Flemington, NJ 08822
Manufacturer: Philips Healthcare
Model #: Ultrasound
Serial #: F07KQV
Contact Name: Anthony Celambrino
Contact Phone: 1(908) 788-611
Timeline
📋
Work Order Created Sep 5, 5:01 PM
Work Order:WO-01302210
Type:PM
Priority:PC
✅
Status: Ready for Release by Mandy NewmanSep 5, 5:22 PM
From:Entered
To:Ready for Release
Duration in Previous:20m
🚨160.8 business days
👷
▶
2
Technician Assigned Apr 29, 2:07 PM
Technician Assigned → Status: Assigned
👷
Status: Assigned by Megan Klose
From:Ready for Release
To:Assigned
Duration in Previous:235d 20h
🗓️
▶
2
Status: Scheduled Apr 29, 7:11 PM
Status: Scheduled → Dispatch Scheduled
📅
Dispatch Scheduled by Megan Klose
Scheduled For:2026-07-08T18:00:00.000+0000
🚨39.6 business days
📅
Dispatch Scheduled by Megan KloseJun 25, 1:43 PM
Scheduled For:2026-07-02T14:00:00.000+0000
⚠️6.0 business days
⏱️
3x Labor Added Jul 2, 10:28 PM
Type:Labor, Travel
Status:Open
Qty:1.5, 50
✔️
Status: Completed by Philmon MehariJul 2, 10:44 PM
From:Scheduled, Completed
To:Completed, Closed
Duration in Previous:64d 3h, 0m
⏳2.2 business days
⏱️
Labor Added Jul 7, 11:22 AM
Type:Labor
Status:Open
Qty:N/A
📋
Status: 07e-Partial Project by Timothy AmburgeyJul 7, 11:29 AM
From:Closed
To:07e-Partial Project
Duration in Previous:4d 12h
⏳3.0 business days
📄
Status: Ready to Bill by Timothy AmburgeyJul 9, 4:16 PM
From:07e-Partial Project
To:Ready to Bill
Duration in Previous:2d 4h
💰
Status: Invoiced by Josh LongwayJul 10, 4:00 AM
From:Ready to Bill
To:Invoiced
Duration in Previous:11h 43m
Bottlenecks
Assigned
Duration: 5.1 business hours (threshold: 4.0 business hours)
Exceeded by 1.1 business hours
Scheduled
Duration: 44.1 business days (threshold: 2.0 business days)
Exceeded by 42.1 business days
Closed
Duration: 2.0 business days (threshold: 1.0 business days)
Exceeded by 1.0 business days
Ready to Bill
Duration: 1.5 business days (threshold: 1.0 business days)