Work Order 360 View

Detailed work order timeline, KPIs, and analysis

← WO Overview

WO-01308751 ↗ ServiceMax

GE HEALTHCARE • Repair • P5

📍 Rutherford Regional Health System — 288 South Ridgecrest Avenue, Rutherfordton NC, 28139

Oct 9, 2025 → Jun 5, 2026

✅ Completed
P5
SLA Clock
5 business days from creation · Target: Oct 20, 2025
✗ SLA Missed (130 biz days late)
Active: 135 biz days
Paused: 26 biz days
Budget: 5 biz days
🕐 Clock stopped: Completed (Jun 5, 2026)
SLA Target
▶ Clock Running
Status: Created
Oct 10 → Oct 10, 2025
0 business days (counted)
Running total: 0 of 5 biz days used
▶ Clock Running
Status: Ready for Scheduling
Oct 10 → Oct 10, 2025
0 business days (counted)
Running total: 0 of 5 biz days used
▶ Clock Running
Status: Assigned
Oct 10 → Oct 16, 2025
3 business days (counted)
Running total: 3 of 5 biz days used
⏸17d
⏸ Clock Paused
Status: Awaiting Parts
Oct 16 → Nov 10, 2025
17 business days (not counted)
22d
▶ Clock Running
Status: Reschedule
Nov 10 → Dec 15, 2025
22 business days (counted)
Running total: 25 of 5 biz days used
▶ Clock Running
Status: Entered
Dec 15 → Dec 15, 2025
0 business days (counted)
Running total: 25 of 5 biz days used
17d
▶ Clock Running
Status: Ready for Scheduling
Dec 15 → Jan 9, 2026
17 business days (counted)
Running total: 42 of 5 biz days used
92d
▶ Clock Running
Status: Assigned
Jan 9 → May 21, 2026
92 business days (counted)
Running total: 134 of 5 biz days used
⏸ Clock Paused
Status: Awaiting Parts
May 21 → Jun 4, 2026
9 business days (not counted)
▶ Clock Running
Status: Reschedule
Jun 4 → Jun 5, 2026
1 business day (counted)
Running total: 135 of 5 biz days used
Created: Oct 10, 2025 Completed: Jun 5, 2026
Business Days Used 135 / 5
0 5d budget +130d over
Show SLA Clock Detail (10 periods)
Period Status Clock Biz Days Running Total
Oct 10 → Oct 10 Created ▶ Running 0 0 / 5
Oct 10 → Oct 10 Ready for Scheduling ▶ Running 0 0 / 5
Oct 10 → Oct 16 Assigned ▶ Running 3 3 / 5
Oct 16 → Nov 10 Awaiting Parts ⏸ Paused 17
Nov 10 → Dec 15 Reschedule ▶ Running 22 25 / 5
Dec 15 → Dec 15 Entered ▶ Running 0 25 / 5
Dec 15 → Jan 9 Ready for Scheduling ▶ Running 17 42 / 5
Jan 9 → May 21 Assigned ▶ Running 92 134 / 5
May 21 → Jun 4 Awaiting Parts ⏸ Paused 9
Jun 4 → Jun 5 Reschedule ▶ Running 1 135 / 5
Dispatch 1.0d
Material Management 27.8d
Coordinators 137.0d
Field Work 0.0d
Billing 11.4d
✗ SLA Missed
Dispatch
1.0 days
Over SLA
Material Management
27.8 days
Over SLA
Coordinators
137.0 days
Over SLA
Field Work
0.0 days
Billing
11.4 days
Over SLA
Created: Oct 10, 2025 Due: Nov 12, 2025 Completed: Jun 5, 2026 (204 days late)
📅
162.0 days Total Age
⏱️
92.5d in Assigned Longest Stage
🔄
12 transitions Status Changes
⚠️
171.3d over Total Delay
📦
2 orders, 0 quotes Parts & Quotes
📝
33 lines Work Details
🚩
4 visits On-Site Trips
📋
Coordinator Scheduling
🚩
4 On-Site Visits (2 reschedules)
4 on-site visits — why were multiple trips needed?
Visit 1 Oct 9, 2025
Visit 2 Nov 21, 2025
Visit 3 Jan 13, 2026
Visit 4 Jun 4, 2026

AI Analysis

Powered by OpenAI
Generating AI analysis...
Completed with significant delays
Invoiced • 308 days old
🚨
Primary Delay 92.5 days stuck in "Assigned"
⏱️
Total Delay 171.3 business days over SLA thresholds

SLA vs Actual Time by Status

Actual (within SLA)
Actual (over SLA)
SLA Target
Entered
1.0d / 0.5d SLA
Assigned
95.9d / 0.5d SLA
Awaiting Parts
27.8d / 3.0d SLA
Reschedule
23.5d / 2.0d SLA
Ready for Scheduling
17.6d / 1.0d SLA
Completed
0.0d / 1.0d SLA
Closed
9.0d / 1.0d SLA
Billing Review
11.4d / 2.0d SLA
Invoice Pending
0.0d / 2.0d SLA

💬 Activities, Notes & Communications

🔒 Internal CSA Notes
JE Unable to close same day. Was waiting on JJ to make billing adjustment.

PO is received and attached.

PO REQUEST SENT

11-21-25- I replaced the logic and main PCB on bed. Bed is still locking out and not allowing me to use any functions. More evaluation will be needed. 01-13-26- I found the PT left side rail sensor wire was cut. Also the side rail cable and side rail pcb
🔧 Work Performed
Replaced Pt Rt siderail board and cables. Replaced Power and Signal coil cables. Tested baed and observed proper operation.
🔍 Technician Findings
Bed locking up intermittently. Siderail cable cut. Left siderail bed down button not working.
⚠️ Problem Description
Unit's patient head left control only either bed up or bed down but not at the same time. Unit also has no knee function on any controls
📄 Description
Bed, Electric

Timeline

📋
2 Work Order Created Oct 9, 8:58 PM
Work Order Created → Labor Added
⏱️
Labor Added
Type: Labor
Status: Open
Qty: 1
📅
2 Status: Ready for Scheduling Oct 10, 8:32 AM
Status: Ready for Scheduling → Technician Assigned
👷
Technician Assigned by Melissa Owens
Technician: a0h5A00000GbsPpQAJ, Christopher Carroll
3.0 business days
💵
2x Expenses Added Oct 15, 11:06 PM
Type: Expenses
Status: Open
Qty: 1
📦
2 Parts Requested Oct 15, 11:21 PM
Parts Requested → Status: Awaiting Parts
📦
Status: Awaiting Parts by Christopher Carroll
From: Assigned
To: Awaiting Parts
Duration in Previous: 5d 14h
🚨 15.1 business days
💵
Expenses Added Nov 5, 9:22 PM
Type: Expenses
Status: Open
Qty: 1
3.3 business days
🔩
2 3x Parts Added Nov 10, 6:21 PM
3x Parts Added → Status: Reschedule
🔄
Status: Reschedule by Keith Fricke
From: Awaiting Parts
To: Reschedule
Duration in Previous: 25d 19h
⚠️ 8.7 business days
⏱️
9x Labor Added Nov 21, 8:13 PM
Type: Labor, Expenses, Travel
Status: Open
Qty: 0.25, 1.75, 6.5, 388
🚨 14.5 business days
🆕
Status: Entered by Melissa Owens Dec 15, 2:08 PM
From: Reschedule, Entered
To: Entered, Ready for Scheduling
Duration in Previous: 34d 19h, 0m
🚨 18.0 business days
👷
2 Technician Assigned Jan 9, 3:04 PM
Technician Assigned → Status: Assigned
👷
Status: Assigned by Melissa Owens
From: Ready for Scheduling
To: Assigned
Duration in Previous: 25d 0h
3.0 business days
💵
2 Expenses Added Jan 13, 2:19 PM
Expenses Added → Expenses Added
💵
Expenses Added
Type: Expenses
Status: Open
Qty: 1
⏱️
3x Labor Added Jan 13, 4:24 PM
Type: Labor, Travel
Status: Open
Qty: 1, 0.25, 6
💵
Expenses Added Jan 14, 7:48 AM
Type: Expenses
Status: Open
Qty: 1
2.0 business days
💵
Expenses Added Jan 15, 4:12 PM
Type: Expenses
Status: Open
Qty: 1
🚨 89.0 business days
📦
2 Parts Requested May 21, 1:35 PM
Parts Requested → Status: Awaiting Parts
📦
Status: Awaiting Parts by Joe Evans
From: Assigned
To: Awaiting Parts
Duration in Previous: 131d 21h
🚨 10.0 business days
🔩
2 7x Parts Added Jun 4, 4:55 PM
7x Parts Added → Status: Reschedule
🔄
Status: Reschedule by Joe Evans
From: Awaiting Parts
To: Reschedule
Duration in Previous: 14d 3h
⏱️
2x Labor Added Jun 4, 5:06 PM
Type: Labor
Status: Open
Qty: 1.75, 3
⏱️
Labor Added Jun 4, 5:18 PM
Type: Labor
Status: Open
Qty: 1.75
✔️
Status: Completed by Joe Evans Jun 5, 10:12 AM
From: Reschedule
To: Completed
Duration in Previous: 17h 16m
🏁
Status: Closed by Joe Evans Jun 5, 10:25 AM
From: Completed
To: Closed
Duration in Previous: 13m
⚠️ 9.0 business days
💵
Status: Billing Review by Hannah Shaw Jun 17, 4:31 PM
From: Closed
To: Billing Review
Duration in Previous: 12d 6h
🚨 11.9 business days
📄
3 Status: Ready to Bill Jul 6, 5:12 PM
Status: Ready to Bill → Invoice Created → Status: Invoiced
🧾
Invoice Created
Invoice Number: SM-266527
💰
Status: Invoiced by Hannah Shaw
From: Invoice Pending
To: Invoiced
Duration in Previous: 0m

Bottlenecks

Entered
Duration: 1.0 business days (threshold: 4.0 business hours)
Exceeded by 4.0 business hours
Assigned
Duration: 3.4 business days (threshold: 4.0 business hours)
Exceeded by 2.9 business days
Awaiting Parts
Duration: 18.0 business days (threshold: 3.0 business days)
Exceeded by 15.0 business days
Reschedule
Duration: 22.1 business days (threshold: 2.0 business days)
Exceeded by 20.1 business days
Ready for Scheduling
Duration: 17.6 business days (threshold: 1.0 business days)
Exceeded by 16.6 business days
Assigned
Duration: 92.5 business days (threshold: 4.0 business hours)
Exceeded by 92.0 business days
Awaiting Parts
Duration: 9.8 business days (threshold: 3.0 business days)
Exceeded by 6.8 business days
Closed
Duration: 9.0 business days (threshold: 1.0 business days)
Exceeded by 8.0 business days
Billing Review
Duration: 11.4 business days (threshold: 2.0 business days)
Exceeded by 9.4 business days

🔗 Related Artifacts

📦
Parts Order 00083656
Closed
📦
Parts Order 00096595
Closed

ℹ️ Work Order Details

Status
Invoiced
Priority
P5
Type
Repair
Branch
N/A
Technician
Michael Swingle
Scheduled
N/A
Created
Oct 9, 8:58 PM
Invoice #
SM-266527

Work Details (33)

Name Type Status Qty Amount Date
WL-02965876 Labor Open 1 $95.00 Oct 9, 9:01 PM
WL-02972638 Expenses Open 1 $0.00 Oct 15, 11:06 PM
WL-02972639 Expenses Open 1 $0.00 Oct 15, 11:06 PM
WL-02997919 Expenses Open 1 $0.00 Nov 5, 9:22 PM
WL-03002567 Parts Open 1 $364.04 Nov 10, 6:21 PM
WL-03002568 Parts Open 1 $536.34 Nov 10, 6:21 PM
WL-03002569 Expenses Open 1 $0.00 Nov 10, 6:21 PM
WL-03017204 Labor Open 0.25 $0.00 Nov 21, 8:13 PM
WL-03017205 Labor Open 1.75 $166.25 Nov 21, 8:13 PM
WL-03017206 Labor Open 6.5 $0.00 Nov 21, 8:13 PM
WL-03017207 Expenses Open 1 $0.00 Nov 21, 8:13 PM
WL-03017208 Expenses Open 1 $0.00 Nov 21, 8:13 PM
WL-03017209 Expenses Open 1 $0.00 Nov 21, 8:13 PM
WL-03017210 Expenses Open 1 $0.00 Nov 21, 8:13 PM
WL-03017211 Travel Open 5 $0.00 Nov 21, 8:13 PM
WL-03017212 Travel Open 388 $0.00 Nov 21, 8:13 PM
WL-03063288 Expenses Open 1 $0.00 Jan 13, 2:19 PM
WL-03063289 Expenses Open 1 $0.00 Jan 13, 2:23 PM
WL-03063554 Labor Open 1 $95.00 Jan 13, 4:24 PM
WL-03063555 Labor Open 0.25 $0.00 Jan 13, 4:24 PM
WL-03063556 Travel Open 6 $0.00 Jan 13, 4:24 PM
WL-03064274 Expenses Open 1 $0.00 Jan 14, 7:48 AM
WL-03066748 Expenses Open 1 $0.00 Jan 15, 4:12 PM
WL-03248835 Parts Open 1 $495.72 Jun 4, 4:55 PM
WL-03248833 Parts Open 1 $60.20 Jun 4, 4:55 PM
WL-03248834 Parts Open 1 $45.09 Jun 4, 4:55 PM
WL-03248836 Parts Open 1 $138.14 Jun 4, 4:55 PM
WL-03248837 Parts Open 1 $96.69 Jun 4, 4:55 PM
WL-03248838 Parts Open 1 $150.96 Jun 4, 4:55 PM
WL-03248839 Expenses Open 1 $0.00 Jun 4, 4:55 PM
WL-03248842 Labor Open 1.75 $0.00 Jun 4, 5:06 PM
WL-03248843 Labor Open 3 $285.00 Jun 4, 5:06 PM
WL-03248855 Labor Open 1.75 $0.00 Jun 4, 5:18 PM

Details