5 business days from creation · Target: Nov 12, 2025
✗ SLA Missed (39 biz days late)
Active: 44 biz days
Paused: 114 biz days
Budget: 5 biz days
🕐 Clock stopped: Completed (Jun 25, 2026)
SLA Target
▶ Clock Running
Status: Created
Nov 4 → Nov 4, 2025
0 business days (counted)
Running total: 0 of 5 biz days used
▶ Clock Running
Status: Ready for Scheduling
Nov 4 → Nov 4, 2025
0 business days (counted)
Running total: 0 of 5 biz days used
29d
▶ Clock Running
Status: Assigned
Nov 4 → Dec 18, 2025
29 business days (counted)
Running total: 29 of 5 biz days used
⏸114d
⏸ Clock Paused
Status: Awaiting Parts
Dec 18 → Jun 3, 2026
114 business days (not counted)
15d
▶ Clock Running
Status: Reschedule
Jun 3 → Jun 25, 2026
15 business days (counted)
Running total: 44 of 5 biz days used
Created: Nov 4, 2025Completed: Jun 25, 2026
Business Days Used44 / 5
05d budget+39d over
Show SLA Clock Detail (5 periods)
Period
Status
Clock
Biz Days
Running Total
Nov 4 → Nov 4
Created
▶ Running
0
0 / 5
Nov 4 → Nov 4
Ready for Scheduling
▶ Running
0
0 / 5
Nov 4 → Dec 18
Assigned
▶ Running
29
29 / 5
Dec 18 → Jun 3
Awaiting Parts
⏸ Paused
114
—
Jun 3 → Jun 25
Reschedule
▶ Running
15
44 / 5
Dispatch0.0d
Material Management114.5d
Coordinators44.9d
Billing24.0d
✗ SLA Missed
Dispatch
0.0 days
Material Management
114.5 days
Over SLA
Coordinators
44.9 days
Over SLA
Billing
24.0 days
Over SLA
Created: Nov 4, 2025
Due: Nov 11, 2025
Completed: Jun 25, 2026 (225 days late)
📅
157.9 daysTotal Age
⏱️
114.5d in Awaiting PartsLongest Stage
🔄
8 transitionsStatus Changes
⚠️
176.8d overTotal Delay
📦
1 orders, 0 quotesParts & Quotes
📝
7 linesWork Details
🚩
3 visitsOn-Site Trips
📋
CoordinatorScheduling
🚩
3 On-Site Visits
(1 reschedule)
3 on-site visits — why were multiple trips needed?
Visit 1Nov 5, 2025
Visit 2Dec 19, 2025
Visit 3Jun 24, 2026
AI Analysis
Powered by OpenAI
Generating AI analysis...
Completed with significant delays
Invoiced • 282 days old
🚨
Primary Delay114.5 days stuck in "Awaiting Parts"
⏱️
Total Delay176.8 business days over SLA thresholds
SLA vs Actual Time by Status
Actual (within SLA)
Actual (over SLA)
SLA Target
Entered
0.0d / 0.5d SLA
Ready for Scheduling
0.0d / 1.0d SLA
Assigned
29.6d / 0.5d SLA
Awaiting Parts
114.5d / 3.0d SLA
Reschedule
15.3d / 2.0d SLA
Closed
2.0d / 1.0d SLA
Billing Review
24.0d / 2.0d SLA
Invoice Pending
0.0d / 2.0d SLA
💬 Activities, Notes & Communications
🔒Internal CSA Notes
7.8.26 hshaw - chat tech to confirm which part# was replaced. Quote showing part# 20877004 and part# 22531604S was shipped. It has a big difference in price.
3.12.2026 Waiting on parts. Checked on 3.12.2026 Texted Mark Franks to check the status on this part. 3.30.2026
🔧Work Performed
11.5.2025 Diag completed
Part number verified
PO Submitted to GE site lead
Pictures taken
12.19.2025 parts are now available on SMX. Parts ordered
6.24.2026
-Replaced the damaged mattress cover with a new OEM replacement cover.
-Inspected the internal foam mattress and verified there was no damage, contamination, or excessive wear.
-Properly installed and secured the new cover, ensuring correct fit and function.
-Performed a final operational inspection of the bed to confirm proper condition.
-Repair completed successfully, and the unit was returned to service.
🔍Technician Findings
-Mattress cover was found damaged and required replacement.
-Internal foam mattress was inspected and found to be in good condition with no tears, fluid intrusion, or structural damage.
-Following installation of the new cover, the mattress met operational standards and was deemed safe for patient use.
-Unit is fully operational and has been returned to service.
⚠️Problem Description
11.4.2025 Mattress cover on unit is damaged and will need to be replaced
PO will be submitted
Clark, Daniel
📄Description
Hillrom P7900 (series) Centrella Smart+ Bed (P7900a, P7900b)
Jul 8, 2026 1:52pm
@Daniel Clark please confirm which part# was replaced. Quote showing part# 20877004 and part# 22531604S was shipped. It has a big difference in price. Thank you.
PDF
PO Request for WO-01312989
Nov 11, 2025
PDF
PO Request for WO-01312989 email
Feb 6, 2026
PDF
po for 602793272 GE Healthcare PO# 4010586291HTM Revision 0
Feb 9, 2026
Timeline
📋
▶
2
Work Order Created Nov 4, 1:44 PM
Work Order Created → Status: Ready for Scheduling
📅
Status: Ready for Scheduling by Sherry Reich
From:Entered
To:Ready for Scheduling
Duration in Previous:0m
👷
▶
2
Status: Assigned Nov 4, 2:00 PM
Status: Assigned → Technician Assigned
👷
Technician Assigned by Abby Jinerson
Technician:Daniel Clark
⏳2.0 business days
⏱️
3x Labor Added Nov 5, 4:16 PM
Type:Labor, Travel
Status:Open
Qty:2, 0.66666666666667, 33
🚨29.0 business days
📦
▶
2
Parts Requested Dec 18, 3:23 PM
Parts Requested → Status: Awaiting Parts
📦
Status: Awaiting Parts by Daniel Clark
From:Assigned
To:Awaiting Parts
Duration in Previous:44d 1h
⏳2.0 business days
⏱️
Labor Added Dec 19, 3:32 PM
Type:Labor
Status:Open
Qty:1
🚨114.0 business days
🔩
▶
2
2x Parts Added Jun 3, 9:45 AM
2x Parts Added → Status: Reschedule
🔄
Status: Reschedule by John Rolston
From:Awaiting Parts
To:Reschedule
Duration in Previous:166d 17h
🚨15.0 business days
⏱️
▶
2
Labor Added Jun 24, 10:05 PM
Labor Added → Status: Completed
✔️
Status: Completed by Daniel Clark
From:Reschedule, Completed
To:Completed, Closed
Duration in Previous:21d 12h, 0m
⏳2.2 business days
💵
Status: Billing Review by Hannah ShawJun 26, 11:39 AM
From:Closed
To:Billing Review
Duration in Previous:1d 13h
🚨24.0 business days
📄
Status: Ready to Bill by Hannah ShawJul 30, 11:00 AM
From:Billing Review, Ready to Bill
To:Ready to Bill, Invoice Pending
Duration in Previous:33d 23h, 0m
💰
▶
2
Status: Invoiced Jul 30, 11:07 AM
Status: Invoiced → Invoice Created
🧾
Invoice Created
Invoice Number:SM-268778
Bottlenecks
Assigned
Duration: 29.6 business days (threshold: 4.0 business hours)
Exceeded by 29.1 business days
Awaiting Parts
Duration: 114.5 business days (threshold: 3.0 business days)
Exceeded by 111.5 business days
Reschedule
Duration: 15.3 business days (threshold: 2.0 business days)
Exceeded by 13.3 business days
Closed
Duration: 2.0 business days (threshold: 1.0 business days)
Exceeded by 1.0 business days
Billing Review
Duration: 24.0 business days (threshold: 2.0 business days)