Work Order 360 View
Detailed work order timeline, KPIs, and analysis
PSM
SLA Clock
Last business day of November 2025 · Target: Nov 28, 2025
✗ SLA Missed (100 biz days late)
🕐 Clock stopped: Canceled (Apr 24, 2026)
▶ Clock Running
Status: Created
Nov 5 → Nov 5, 2025
0 business days (counted)
Running total: 0 of ? biz days used
▶ Clock Running
Status: Scheduled
Nov 5 → Nov 5, 2025
0 business days (counted)
Running total: 0 of ? biz days used
33d
▶ Clock Running
Status: Ready for Scheduling
Nov 5 → Dec 26, 2025
33 business days (counted)
Running total: 33 of ? biz days used
82d
▶ Clock Running
Status: Scheduled
Dec 26 → Apr 24, 2026
82 business days (counted)
Running total: 115 of ? biz days used
▶ Clock Running
Status: Ready for Scheduling
Apr 24 → Apr 24, 2026
0 business days (counted)
Running total: 115 of ? biz days used
Created: Nov 5, 2025
Canceled: Apr 24, 2026
Show SLA Clock Detail (5 periods)
| Period |
Status |
Clock |
Biz Days |
Running Total |
| Nov 5 → Nov 5 |
Created |
▶ Running
|
0 |
0 |
| Nov 5 → Nov 5 |
Scheduled |
▶ Running
|
0 |
0 |
| Nov 5 → Dec 26 |
Ready for Scheduling |
▶ Running
|
33 |
33 |
| Dec 26 → Apr 24 |
Scheduled |
▶ Running
|
82 |
115 |
| Apr 24 → Apr 24 |
Ready for Scheduling |
▶ Running
|
0 |
115 |
Coordinators
115.8 days
Over SLA
Created: Nov 5, 2025
Due: Dec 31, 2026
Completed: Apr 24, 2026 (251 days early)
⏱️
82.2d in Scheduled
Longest Stage
🔄
4 transitions
Status Changes
⚠️
112.8d over
Total Delay
📦
0 orders, 0 quotes
Parts & Quotes
AI Analysis
Powered by OpenAI
Generating AI analysis...
🚨
Primary Delay
82.2 days stuck in "Scheduled"
⏱️
Total Delay
112.8 business days over SLA thresholds
SLA vs Actual Time by Status
Ready for Scheduling
33.7d
/ 1.0d SLA
Scheduled
82.2d
/ 2.0d SLA
💬 Activities, Notes & Communications
🔒
Internal CSA Notes
11/5/2025 1400 CM ack msg; LM w/SC, TP, JaB; TP other shift; 11/6/2025 1403 JaB decline; 11/10/2025 1351 CM LM w/EZ; 11/12/2025 1305 LM w/Amy re NAR; 12/26/2025 1048 ES avail; 1053 LM w/Amy re cnfm; 1356 Amy cnfm; 1410 ack cnfm; LM w/ES; 1703 ES ack cnfm; 4/24/26 1119 assign cxl; LM w/ES; 1236 ES ack cxl
Timeline
📋
🗓️
From:
Ready for Scheduling, Scheduled
To:
Scheduled, Ready for Scheduling
Duration in Previous:
0m
👷
🗓️
From:
Ready for Scheduling
To:
Scheduled
Duration in Previous:
51d 3h
📅
From:
Scheduled
To:
Ready for Scheduling
Duration in Previous:
118d 17h
🚫
From:
Ready for Scheduling
To:
Canceled
Duration in Previous:
42m
Bottlenecks
Ready for Scheduling
Duration: 33.6 business days (threshold: 1.0 business days)
Exceeded by 32.6 business days
Scheduled
Duration: 82.2 business days (threshold: 2.0 business days)
Exceeded by 80.2 business days