📍 Main Street Radiology — 37th Ave 13625, Flushing NY, 11354
Nov 10, 2025 → Sep 9, 2026
✅ Completed
PC
SLA Clock
Per client agreement · Target: Oct 30, 2026
✓ SLA Met (36 biz days early)
Active: 60 biz days
Paused: 146 biz days
🕐 Clock stopped: Tech Off Site (Sep 9, 2026)
▶ Clock Running
Status: Created
Nov 10 → Nov 10, 2025
0 business days (counted)
Running total: 0 of ? biz days used
⏸146d
⏸ Clock Paused
Status: Ready for Release
Nov 10 → Jun 12, 2026
146 business days (not counted)
60d
▶ Clock Running
Status: Scheduled
Jun 12 → Sep 9, 2026
60 business days (counted)
Running total: 60 of ? biz days used
▶ Clock Running
Status: Tech On Site
Sep 9 → Sep 9, 2026
0 business days (counted)
Running total: 60 of ? biz days used
Created: Nov 10, 2025Tech Off Site: Sep 9, 2026
Show SLA Clock Detail (4 periods)
Period
Status
Clock
Biz Days
Running Total
Nov 10 → Nov 10
Created
▶ Running
0
0
Nov 10 → Jun 12
Ready for Release
⏸ Paused
146
—
Jun 12 → Sep 9
Scheduled
▶ Running
60
60
Sep 9 → Sep 9
Tech On Site
▶ Running
0
60
Dispatch0.0d
Holding146.9d (excluded)
Coordinators61.0d
Field Work0.9d
Billing1.5d
✓ SLA Met
Dispatch
0.0 days
Holding(excluded from total)
146.9 days
Coordinators
61.0 days
Over SLA
Field Work
0.9 days
Billing
1.5 days
Over SLA
Created: Nov 10, 2025
Due: Oct 30, 2026
Completed: Sep 9, 2026 (51 days early)
📅
206.9 daysTotal Age
⏱️
146.9d in Ready for ReleaseLongest Stage
🔄
9 transitionsStatus Changes
⚠️
64.6d overTotal Delay
📦
0 orders, 0 quotesParts & Quotes
📝
4 linesWork Details
🏠
1 visitOn-Site Trips
👤
Self-ScheduledScheduling
AI Analysis
Powered by OpenAI
Generating AI analysis...
Completed with significant delays
Invoiced • 346 days old
🚨
Primary Delay146.9 days stuck in "Ready for Release"
⏱️
Total Delay64.6 business days over SLA thresholds
SLA vs Actual Time by Status
Actual (within SLA)
Actual (over SLA)
SLA Target
Entered
0.0d / 0.5d SLA
Ready for Release
146.9d
Scheduled
61.0d / 2.0d SLA
Tech On Site
0.8d / 1.0d SLA
Tech Off Site
0.1d / 2.0d SLA
Completed
0.0d / 1.0d SLA
Closed
6.1d / 1.0d SLA
07e-Partial Project
0.7d
Ready to Bill
1.5d / 1.0d SLA
💬 Activities, Notes & Communications
🔒Internal CSA Notes
06/11/2026 Rbailey - Rcvd email from Jin Ling for Vivian to come onsite September 9 at 10. Sending email and Advising Planner to Dispatch
06/11/2026 Rbailey - Called 347.376.2626 for Jin. NA Left VM. Sending email with updated time for 2nd proposed date.
06/04/2026 DMalloy - First Contact email sent to customer confirming Jing Lin the device location, serial number and proposed a date and time for a visit.
jlin@msrad.com
🔧Work Performed
EPIQ Elite Diagnostic Ultrasound System - IP 92416067 - SN US821B2165
⚠️Problem Description
EPIQ Elite Diagnostic Ultrasound System - IP 92416067 - SN US821B2165
📞Call Description
PM - Contract - BG Required PM
📋
0-0-0
Completed Sep 23, 2026
Tech Supervisor Spot Check
# of Critical Defects: 0
# of Major Defects: 0
# of Minor Defects: 0
# of EMSAR Defects: 0
Ultrasound - PM
a. Tools : Electrical Safety & Phantom – YES
b. Prontoforms – uploaded and correct template – YES
c. CSR – signed and uploaded to ServiceMax - YES
📅
WO-01313985 - Preventive Maintenance - DD: 10/30/2026 - - Ultrasound - Flushing - Main Street Radiology
Sep 9, 2026 10:00am – 12:00pm
Work Order: WO-01313985
Account: PHILIPS HEALTHCARE
Customer Case Number: WO-13499218
Location: Main Street Radiology
Address: 37th Ave 13625, Flushing, NY 11354
Manufacturer: Philips Healthcare
Model #: Ultrasound
Serial #: US821B2165
Contact Name: Jing Lin
Contact Phone: (347) 376-2626
C
Timeline
📋
Work Order Created Nov 10, 11:26 AM
Work Order:WO-01313985
Type:Preventive Maintenance
Priority:PC
✅
Status: Ready for Release by Mandy NewmanNov 10, 11:42 AM