📍 BAYLOR SCOTT & WHITE MEDICAL CENTER IRVING — 1901 N MACARTHUR BLVD, IRVING TX, 75061
Dec 12, 2025 → Feb 23, 2026
✅ Completed
PC
SLA Clock
Per client agreement · Target: Feb 28, 2026
✓ SLA Met (4 biz days early)
Active: 3 biz days
Paused: 44 biz days
🕐 Clock stopped: Completed (Feb 23, 2026)
▶ Clock Running
Status: Created
Dec 12 → Dec 15, 2025
1 business day (counted)
Running total: 1 of ? biz days used
⏸44d
⏸ Clock Paused
Status: Ready for Release
Dec 15 → Feb 19, 2026
44 business days (not counted)
▶ Clock Running
Status: Scheduled
Feb 19 → Feb 23, 2026
2 business days (counted)
Running total: 3 of ? biz days used
▶ Clock Running
Status: Tech On Site
Feb 23 → Feb 23, 2026
0 business days (counted)
Running total: 3 of ? biz days used
▶ Clock Running
Status: Scheduled
Feb 23 → Feb 23, 2026
0 business days (counted)
Running total: 3 of ? biz days used
▶ Clock Running
Status: Tech On Site
Feb 23 → Feb 23, 2026
0 business days (counted)
Running total: 3 of ? biz days used
Created: Dec 12, 2025Completed: Feb 23, 2026
Show SLA Clock Detail (6 periods)
Period
Status
Clock
Biz Days
Running Total
Dec 12 → Dec 15
Created
▶ Running
1
1
Dec 15 → Feb 19
Ready for Release
⏸ Paused
44
—
Feb 19 → Feb 23
Scheduled
▶ Running
2
3
Feb 23 → Feb 23
Tech On Site
▶ Running
0
3
Feb 23 → Feb 23
Scheduled
▶ Running
0
3
Feb 23 → Feb 23
Tech On Site
▶ Running
0
3
Dispatch2.0d
Holding44.8d (excluded)
Coordinators3.1d
Field Work0.7d
Billing18.9d
✓ SLA Met
Dispatch
2.0 days
Over SLA
Holding(excluded from total)
44.8 days
Coordinators
3.1 days
Over SLA
Field Work
0.7 days
Billing
18.9 days
Over SLA
Created: Dec 12, 2025
Due: Feb 28, 2026
Completed: Feb 23, 2026 (5 days early)
📅
48.0 daysTotal Age
⏱️
44.8d in Ready for ReleaseLongest Stage
🔄
13 transitionsStatus Changes
⚠️
20.2d overTotal Delay
📦
0 orders, 0 quotesParts & Quotes
📝
9 linesWork Details
🏠
2 visitsOn-Site Trips
👤
Self-ScheduledScheduling
🔄
2 On-Site Visits
2 on-site visits — follow-up trip required
👤 Self-scheduled by Eric Mancerella — scheduling delays attributed to technician, not coordinators
Visit 1Feb 23, 2026
AI Analysis
Powered by OpenAI
Generating AI analysis...
Completed with significant delays
Invoiced • 244 days old
🚨
Primary Delay44.8 days stuck in "Ready for Release"
⏱️
Total Delay20.2 business days over SLA thresholds
SLA vs Actual Time by Status
Actual (within SLA)
Actual (over SLA)
SLA Target
Entered
2.0d / 0.5d SLA
Ready for Release
44.8d
Scheduled
3.1d / 2.0d SLA
Tech On Site
0.6d / 1.0d SLA
Completed
0.2d / 1.0d SLA
Closed
5.2d / 1.0d SLA
Ready to Bill
16.7d / 1.0d SLA
WO Correction Needed
2.1d
Invoice Pending
0.0d / 2.0d SLA
💬 Activities, Notes & Communications
🔒Internal CSA Notes
02/23/2026 SRobinson- Created follow up WO as requested. (WO-01353397)
02/19/2026 DMalloy - Dispatched for FSE Eric to walk in on Monday 2/23.
02/19/2026 DMalloy - Called 972.990.8287 for Laura Hodnett / Keely McMacken located on PWO for this locaiton. No answer. left a VM for a call back. Following up with an email.
laura.hodnett@bswhealth.org
daniel.bollinger@bjc.org
ataisha.washington@bswhealth.org
🔧Work Performed
"Template Name:
Template Description:
Problem Found:
Action Taken: Completed FMI 78101 by installing SW Version R4.5 and communicated with customer to scrap previous software versions.
Verification Test: Performed Probe and Connectors Checks for all probes. Confirmed all probes pass. Completed all Peripheral Checks-system passed. Completed full system diagnostics-system passed.
Template Name:
Template Description:
Problem Found:
Action Taken: “Completed FMI 78101 by installing new supplied batteries / Batteries installed by
customer and dispose of old batteries according to local regulation”.
Verification Test: “Performed battery charging test - verified after 10 minutes, the scan time increased. Completed full system diagnostics-system passed. Equipment passed all required tests and has been returned to the customer fully functional”."
🔍Technician Findings
78101
⚠️Problem Description
FMI 78101D: Venue Go Thermal Event due to battery Purpose: Each affected system will have a SW Version R4.5 update installed. FMI Type: Mandatory Recall FMI For code 2, 3, 4 and 5 closures, please reach out to FMI admin team at TCS.FMIAdmin@gehealthcare.com or 8668836784 ? OPT. 5 for assistance in closing and correct objective evidence attachment to Activity/SR.
📄Description
GE Healthcare - Venue Go Ultrasound
📞Call Description
FMI 78101
📧
Email: Urgent Schedule Attempt - Field Action Notice - FMI 78101 - GE Healthcare - Venue Go/Fit Thermal Event - BAYLOR SCOTT & WHITE MEDICAL CENTER IRVING - IRVING, TX - WO-01325311
Completed Feb 19, 2026
To: laura.hodnett@bswhealth.org; daniel.bollinger@bjc.org; ataisha.washington@bswhealth.org
CC: central.scheduling@emsar.com; fmessak@emsar.com; eric.mancerella@emsar.com
BCC: deon.malloy@emsar.com
Attachment: Vendor Letter for Customers 78101 EMSAR.pdf, FMI 78101 Customer Letter_DOC3115777_Rev2.pdf
Subject: Urgent Schedule Attempt - Field Action Notice - FMI 78101 - GE Healthcare - Venue Go/Fit Thermal Event - BAYLOR SCOTT & WHITE MEDICAL CENTER IRVING - IRVING, TX - WO-01325311
Body:
Hello
📧
Live Call_Followed Up With Email
Completed Feb 19, 2026
02/19/2026 DMalloy - Called 972.990.8287 for Laura Hodnett / Keely McMacken located on PWO for this locaiton. No answer. left a VM for a call back. Following up with an email.
laura.hodnett@bswhealth.org
daniel.bollinger@bjc.org
ataisha.washington@bswhealth.org
📅
WO-01325311 - FCO - Venue Go Ultrasound - IRVING - BAYLOR SCOTT & WHITE MEDICAL CENTER IRVING
Feb 22, 2026 7:00pm – 7:00pm
Work Order: WO-01325311
Account: GE Healthcare FMI
Customer Case Number: 1-554880157876, 1-554907997460
Location: BAYLOR SCOTT & WHITE MEDICAL CENTER IRVING
Address: 1901 N MACARTHUR BLVD, IRVING, TX 75061
Manufacturer: GE Healthcare
Model #: Venue Go Ultrasound
Serial #: VGD000913
Contact Name:
Co
JPG
VGD000913 INFORMATION REPORT
Feb 23, 2026
JPG
VGD000913 BATTERIES
Feb 23, 2026
JPG
VGD000913 NO WORKLIST
Feb 23, 2026
JPG
VGD000913 HOSP. WIFI
Feb 23, 2026
PDF
VGD000913 COMPLETION REPORT
Feb 23, 2026
JPG
VGD000913 SOFTWARE
Feb 23, 2026
JPG
VGD000913 SERIAL #
Feb 23, 2026
Timeline
📋
Work Order Created Dec 12, 11:06 AM
Work Order:WO-01325311
Type:FCO
Priority:PC
⏳2.0 business days
✅
Status: Ready for Release by Mandy NewmanDec 15, 12:18 PM