📍 METHODIST HOSPITAL — 7700 FLOYD CURL DR, SAN ANTONIO TX, 78229
Dec 12, 2025 → Feb 13, 2026
✅ Completed
PC
SLA Clock
Per client agreement · Target: Feb 28, 2026
✓ SLA Met (9 biz days early)
Active: 16 biz days
Paused: 26 biz days
🕐 Clock stopped: Completed (Feb 14, 2026)
▶ Clock Running
Status: Created
Dec 12 → Dec 15, 2025
1 business day (counted)
Running total: 1 of ? biz days used
⏸25d
⏸ Clock Paused
Status: Ready for Release
Dec 15 → Jan 22, 2026
25 business days (not counted)
▶ Clock Running
Status: Scheduled
Jan 22 → Jan 22, 2026
0 business days (counted)
Running total: 1 of ? biz days used
⏸ Clock Paused
Status: Awaiting Parts
Jan 22 → Jan 23, 2026
1 business day (not counted)
15d
▶ Clock Running
Status: Scheduled
Jan 23 → Feb 13, 2026
15 business days (counted)
Running total: 16 of ? biz days used
▶ Clock Running
Status: Tech On Site
Feb 13 → Feb 14, 2026
0 business days (counted)
Running total: 16 of ? biz days used
Created: Dec 12, 2025Completed: Feb 14, 2026
Show SLA Clock Detail (6 periods)
Period
Status
Clock
Biz Days
Running Total
Dec 12 → Dec 15
Created
▶ Running
1
1
Dec 15 → Jan 22
Ready for Release
⏸ Paused
25
—
Jan 22 → Jan 22
Scheduled
▶ Running
0
1
Jan 22 → Jan 23
Awaiting Parts
⏸ Paused
1
—
Jan 23 → Feb 13
Scheduled
▶ Running
15
16
Feb 13 → Feb 14
Tech On Site
▶ Running
0
16
Dispatch2.0d
Material Management1.8d
Holding25.8d (excluded)
Coordinators15.4d
Field Work1.0d
Billing13.2d
✓ SLA Met
Dispatch
2.0 days
Over SLA
Material Management
1.8 days
Holding(excluded from total)
25.8 days
Coordinators
15.4 days
Over SLA
Field Work
1.0 days
Billing
13.2 days
Over SLA
Created: Dec 12, 2025
Due: Feb 28, 2026
Completed: Feb 14, 2026 (14 days early)
📅
43.0 daysTotal Age
⏱️
25.8d in Ready for ReleaseLongest Stage
🔄
8 transitionsStatus Changes
⚠️
26.9d overTotal Delay
📦
1 orders, 0 quotesParts & Quotes
📝
10 linesWork Details
🏠
1 visitOn-Site Trips
👤
Self-ScheduledScheduling
AI Analysis
Powered by OpenAI
Generating AI analysis...
Completed with significant delays
Invoiced • 244 days old
🚨
Primary Delay25.8 days stuck in "Ready for Release"
⏱️
Total Delay26.9 business days over SLA thresholds
SLA vs Actual Time by Status
Actual (within SLA)
Actual (over SLA)
SLA Target
Entered
2.0d / 0.5d SLA
Ready for Release
25.8d
Awaiting Parts
1.8d / 3.0d SLA
Scheduled
15.4d / 2.0d SLA
Tech On Site
1.0d / 1.0d SLA
Closed
0.0d / 1.0d SLA
Ready to Bill
13.0d / 1.0d SLA
Invoice Pending
0.2d / 2.0d SLA
💬 Activities, Notes & Communications
🔒Internal CSA Notes
01/22/2026 Brod - called 2104406916 to speak to Angel Mata, went to vm left message to have FSE onsite for 01/26. following up in email to Angel.Mata@gehealthcare.com
01/16/2026 Brod - called 2107785902 to speak to Stephen went to vm left message, following up in email 01/08/2026 MHamersley - called 210-778-5902, Stephen Larabee, (he was POC for Vents) call went to VM/LM; sent email: Stephen.Larabee@gehealthcare.com
🔧Work Performed
"Template Name:
Template Description:
Problem Found:
Action Taken: “Completed FMI 78101 by installing SW Version R3.4 or R3.5 and communicated with customer to scrap previous software versions”.
Verification Test: “Performed Probe and Connectors Checks for all probes. Confirmed all probes pass. Completed all Peripheral Checks-system passed. Completed full system diagnostics-system passed. Equipment passed all required tests and has been returned to the customer fully functional”.
Template Name:
Template Description:
Problem Found:
Action Taken: “Completed FMI 78101 by installing new supplied batteries / Batteries installed by customer and dispose of old batteries according to local regulation”.
Verification Test: “Performed battery charging test - verified after 10 minutes, the scan time increased. Completed full system diagnostics-system passed. Equipment passed all required tests and has been returned to the customer fully functional”."
🔍Technician Findings
FMI implemented.
⚠️Problem Description
FMI 78101B: Venue Go Thermal Event due to battery Purpose: Each affected system will have a SW Version R3.5 update installed. FMI Type: Mandatory Recall FMI For code 2, 3, 4 and 5 closures, please reach out to FMI admin team at TCS.FMIAdmin@gehealthcare.com or 8668836784 – OPT. 5 for assistance in closing and correct objective evidence attachment to Activity/SR.
📄Description
GE Healthcare - Venue Go Ultrasound
📞Call Description
FMI 78101
📞
Live Call_ Left Message
Completed Jan 22, 2026
01/22/2026 Brod - called 2104406916 to speak to Angel Mata, went to vm left message to have FSE onsite for 01/26. following up in email to Angel.Mata@gehealthcare.com
📅
WO-01325783 - FCO - Venue Go Ultrasound - SAN ANTONIO - METHODIST HOSPITAL
Jan 25, 2026 7:00pm – 7:00pm
Work Order: WO-01325783
Account: GE Healthcare FMI
Customer Case Number: 1-554879921597, 1-554907727971
Location: METHODIST HOSPITAL
Address: 7700 FLOYD CURL DR, SAN ANTONIO, TX 78229
Manufacturer: GE Healthcare
Model #: Venue Go Ultrasound
Serial #: VGC007642
Contact Name:
Contact Phone:
Contact
PDF
VGC007642_Product Label Pic
Feb 13, 2026
PDF
VGC007642_Admin System Admin 1
Feb 13, 2026
PDF
VGC007642_About System Version 1
Feb 13, 2026
PDF
VGC007642_Batteries
Feb 13, 2026
PDF
VGC007642_Self Test Post FMI
Feb 13, 2026
Timeline
📋
Work Order Created Dec 12, 11:06 AM
Work Order:WO-01325783
Type:FCO
Priority:PC
⏳2.0 business days
✅
Status: Ready for Release by Mandy NewmanDec 15, 12:18 PM