📍 Sam's Club #6376 — 4062 Lyndon B. Johnson Freeway, Addison TX, 75001
Jan 6, 2026 → Oct 21, 2026
✅ Completed
PSM
SLA Clock
Last business day of January 2026 · Target: Jan 30, 2026
✗ SLA Missed (52 biz days late)
Active: 70 biz days
Paused: 129 biz days
🕐 Clock stopped: Completed (Oct 21, 2026)
▶ Clock Running
Status: Created
Jan 6 → Jan 7, 2026
1 business day (counted)
Running total: 1 of ? biz days used
⏸ Clock Paused
Status: Ready for Release
Jan 7 → Jan 14, 2026
5 business days (not counted)
▶ Clock Running
Status: Assigned
Jan 14 → Jan 14, 2026
0 business days (counted)
Running total: 1 of ? biz days used
26d
▶ Clock Running
Status: Scheduled
Jan 14 → Feb 23, 2026
26 business days (counted)
Running total: 27 of ? biz days used
▶ Clock Running
Status: Reschedule
Feb 23 → Feb 24, 2026
1 business day (counted)
Running total: 28 of ? biz days used
▶ Clock Running
Status: Entered
Feb 24 → Feb 24, 2026
0 business days (counted)
Running total: 28 of ? biz days used
⏸ Clock Paused
Status: Ready for Release
Feb 24 → Mar 19, 2026
17 business days (not counted)
▶ Clock Running
Status: Assigned
Mar 19 → Mar 19, 2026
0 business days (counted)
Running total: 28 of ? biz days used
▶ Clock Running
Status: Scheduled
Mar 19 → Mar 26, 2026
5 business days (counted)
Running total: 33 of ? biz days used
▶ Clock Running
Status: Entered
Mar 26 → Mar 26, 2026
0 business days (counted)
Running total: 33 of ? biz days used
⏸ Clock Paused
Status: Ready for Release
Mar 26 → Apr 15, 2026
14 business days (not counted)
▶ Clock Running
Status: Assigned
Apr 15 → Apr 15, 2026
0 business days (counted)
Running total: 33 of ? biz days used
▶ Clock Running
Status: Entered
Apr 15 → Apr 15, 2026
0 business days (counted)
Running total: 33 of ? biz days used
⏸ Clock Paused
Status: Ready for Release
Apr 15 → May 6, 2026
15 business days (not counted)
▶ Clock Running
Status: Assigned
May 6 → May 6, 2026
0 business days (counted)
Running total: 33 of ? biz days used
▶ Clock Running
Status: Scheduled
May 6 → May 12, 2026
4 business days (counted)
Running total: 37 of ? biz days used
▶ Clock Running
Status: Entered
May 12 → May 12, 2026
0 business days (counted)
Running total: 37 of ? biz days used
⏸ Clock Paused
Status: Ready for Release
May 12 → May 29, 2026
12 business days (not counted)
▶ Clock Running
Status: Assigned
May 29 → May 29, 2026
0 business days (counted)
Running total: 37 of ? biz days used
⏸16d
⏸ Clock Paused
Status: Ready for Release
May 29 → Jun 23, 2026
16 business days (not counted)
▶ Clock Running
Status: Assigned
Jun 23 → Jun 23, 2026
0 business days (counted)
Running total: 37 of ? biz days used
⏸31d
⏸ Clock Paused
Status: Ready for Release
Jun 23 → Aug 6, 2026
31 business days (not counted)
▶ Clock Running
Status: Assigned
Aug 6 → Aug 6, 2026
0 business days (counted)
Running total: 37 of ? biz days used
▶ Clock Running
Status: Scheduled
Aug 6 → Aug 6, 2026
0 business days (counted)
Running total: 37 of ? biz days used
▶ Clock Running
Status: Entered
Aug 6 → Aug 6, 2026
0 business days (counted)
Running total: 37 of ? biz days used
⏸19d
⏸ Clock Paused
Status: Ready for Release
Aug 6 → Sep 2, 2026
19 business days (not counted)
▶ Clock Running
Status: Ready for Scheduling
Sep 2 → Sep 3, 2026
1 business day (counted)
Running total: 38 of ? biz days used
▶ Clock Running
Status: Assigned
Sep 3 → Sep 21, 2026
11 business days (counted)
Running total: 49 of ? biz days used
21d
▶ Clock Running
Status: Scheduled
Sep 21 → Oct 21, 2026
21 business days (counted)
Running total: 70 of ? biz days used
▶ Clock Running
Status: Tech On Site
Oct 21 → Oct 21, 2026
0 business days (counted)
Running total: 70 of ? biz days used
Created: Jan 6, 2026Completed: Oct 21, 2026
Show SLA Clock Detail (30 periods)
Period
Status
Clock
Biz Days
Running Total
Jan 6 → Jan 7
Created
▶ Running
1
1
Jan 7 → Jan 14
Ready for Release
⏸ Paused
5
—
Jan 14 → Jan 14
Assigned
▶ Running
0
1
Jan 14 → Feb 23
Scheduled
▶ Running
26
27
Feb 23 → Feb 24
Reschedule
▶ Running
1
28
Feb 24 → Feb 24
Entered
▶ Running
0
28
Feb 24 → Mar 19
Ready for Release
⏸ Paused
17
—
Mar 19 → Mar 19
Assigned
▶ Running
0
28
Mar 19 → Mar 26
Scheduled
▶ Running
5
33
Mar 26 → Mar 26
Entered
▶ Running
0
33
Mar 26 → Apr 15
Ready for Release
⏸ Paused
14
—
Apr 15 → Apr 15
Assigned
▶ Running
0
33
Apr 15 → Apr 15
Entered
▶ Running
0
33
Apr 15 → May 6
Ready for Release
⏸ Paused
15
—
May 6 → May 6
Assigned
▶ Running
0
33
May 6 → May 12
Scheduled
▶ Running
4
37
May 12 → May 12
Entered
▶ Running
0
37
May 12 → May 29
Ready for Release
⏸ Paused
12
—
May 29 → May 29
Assigned
▶ Running
0
37
May 29 → Jun 23
Ready for Release
⏸ Paused
16
—
Jun 23 → Jun 23
Assigned
▶ Running
0
37
Jun 23 → Aug 6
Ready for Release
⏸ Paused
31
—
Aug 6 → Aug 6
Assigned
▶ Running
0
37
Aug 6 → Aug 6
Scheduled
▶ Running
0
37
Aug 6 → Aug 6
Entered
▶ Running
0
37
Aug 6 → Sep 2
Ready for Release
⏸ Paused
19
—
Sep 2 → Sep 3
Ready for Scheduling
▶ Running
1
38
Sep 3 → Sep 21
Assigned
▶ Running
11
49
Sep 21 → Oct 21
Scheduled
▶ Running
21
70
Oct 21 → Oct 21
Tech On Site
▶ Running
0
70
Holding135.9d (excluded)
Coordinators75.0d
Field Work0.3d
✗ SLA Missed
Holding(excluded from total)
135.9 days
Coordinators
75.0 days
Over SLA
Field Work
0.3 days
Created: Jan 6, 2026
Due: Dec 31, 2026
Completed: Oct 21, 2026 (71 days early)
📅
199.6 daysTotal Age
⏱️
31.6d in Ready for ReleaseLongest Stage
🔄
22 transitionsStatus Changes
⚠️
63.1d overTotal Delay
📦
0 orders, 0 quotesParts & Quotes
📝
5 linesWork Details
🏠
1 visitOn-Site Trips
👤
Self-ScheduledScheduling
AI Analysis
Powered by OpenAI
Generating AI analysis...
Completed with significant delays
Closed • 288 days old
🚨
Primary Delay31.6 days stuck in "Ready for Release"
⏱️
Total Delay63.1 business days over SLA thresholds
SLA vs Actual Time by Status
Actual (within SLA)
Actual (over SLA)
SLA Target
On Hold
1.6d
Ready for Release
134.3d
Scheduled
59.5d / 2.0d SLA
Reschedule
2.0d / 2.0d SLA
Assigned
11.7d / 0.5d SLA
Ready for Scheduling
1.8d / 1.0d SLA
Tech On Site
0.3d / 1.0d SLA
💬 Activities, Notes & Communications
🔧Work Performed
I completed the PM on the unit. I function tested the unit and all passed. I returned the unit to service.
🔍Technician Findings
Pm
⚠️Problem Description
Please Perform a PM on this Kiosk and attach all required photos from Checklist Regardless if a PM was completed or not a Checklist and photos are required as well as a signed field service report for every work order If a follow up is needed: Confirm with Tech support, select New issue, enter in the troubleshooting performed and part needed for the follow up in the follow up notes field Trunk stock work order: email dispatch@emsar.com with current work order # and the description of the repair that is required to be performed prior to PM completion (Example LED lights, bamboo seat replacement, Leveler replacement etc. all parts that can be found in your trunk stock ) Link to Work Instructions & Checklist on last page: SZZT (Higi Green) https://emsar-portal1.sharepoint.com/SOPs%20and%20Work%20Instructions/Higi%20&%20Legacy%20Kiosk%20Group/Higi%20Green/WI-ST-310%20Higi%20Green%20Preventative%20Maintenance%20009%20DCR652.pdf