Work Order 360 View

Detailed work order timeline, KPIs, and analysis

← WO Overview

WO-01329886 ↗ ServiceMax

HIGI LLC • Preventive Maintenance • PSM

📍 Sam's Club #6338 — 1405 Earl Rudder Fwy S, College Station TX, 77845

Jan 6, 2026 → Jul 1, 2026

✅ Completed
PSM
SLA Clock
Last business day of January 2026 · Target: Jan 30, 2026
✗ SLA Missed (8 biz days late)
Active: 26 biz days
Paused: 97 biz days
🕐 Clock stopped: Completed (Jul 2, 2026)
▶ Clock Running
Status: Created
Jan 6 → Jan 7, 2026
1 business day (counted)
Running total: 1 of ? biz days used
⏸38d
⏸ Clock Paused
Status: Ready for Release
Jan 7 → Mar 4, 2026
38 business days (not counted)
▶ Clock Running
Status: Assigned
Mar 4 → Mar 4, 2026
0 business days (counted)
Running total: 1 of ? biz days used
▶ Clock Running
Status: Scheduled
Mar 4 → Mar 16, 2026
8 business days (counted)
Running total: 9 of ? biz days used
11d
▶ Clock Running
Status: Reschedule
Mar 16 → Mar 31, 2026
11 business days (counted)
Running total: 20 of ? biz days used
▶ Clock Running
Status: Entered
Mar 31 → Mar 31, 2026
0 business days (counted)
Running total: 20 of ? biz days used
⏸21d
⏸ Clock Paused
Status: Ready for Release
Mar 31 → Apr 29, 2026
21 business days (not counted)
▶ Clock Running
Status: Assigned
Apr 29 → Apr 29, 2026
0 business days (counted)
Running total: 20 of ? biz days used
▶ Clock Running
Status: Scheduled
Apr 29 → May 1, 2026
2 business days (counted)
Running total: 22 of ? biz days used
▶ Clock Running
Status: Entered
May 1 → May 1, 2026
0 business days (counted)
Running total: 22 of ? biz days used
⏸ Clock Paused
Status: Ready for Release
May 1 → May 6, 2026
3 business days (not counted)
▶ Clock Running
Status: Assigned
May 6 → May 6, 2026
0 business days (counted)
Running total: 22 of ? biz days used
▶ Clock Running
Status: Entered
May 6 → May 6, 2026
0 business days (counted)
Running total: 22 of ? biz days used
⏸ Clock Paused
Status: Ready for Release
May 6 → May 13, 2026
5 business days (not counted)
▶ Clock Running
Status: Assigned
May 13 → May 13, 2026
0 business days (counted)
Running total: 22 of ? biz days used
▶ Clock Running
Status: Scheduled
May 13 → May 15, 2026
2 business days (counted)
Running total: 24 of ? biz days used
▶ Clock Running
Status: Entered
May 15 → May 15, 2026
0 business days (counted)
Running total: 24 of ? biz days used
⏸ Clock Paused
Status: Ready for Release
May 15 → May 21, 2026
4 business days (not counted)
▶ Clock Running
Status: Assigned
May 21 → May 21, 2026
0 business days (counted)
Running total: 24 of ? biz days used
▶ Clock Running
Status: Scheduled
May 21 → May 22, 2026
1 business day (counted)
Running total: 25 of ? biz days used
▶ Clock Running
Status: Entered
May 22 → May 22, 2026
0 business days (counted)
Running total: 25 of ? biz days used
⏸18d
⏸ Clock Paused
Status: Ready for Release
May 22 → Jun 18, 2026
18 business days (not counted)
▶ Clock Running
Status: Assigned
Jun 18 → Jun 18, 2026
0 business days (counted)
Running total: 25 of ? biz days used
▶ Clock Running
Status: Scheduled
Jun 18 → Jun 18, 2026
0 business days (counted)
Running total: 25 of ? biz days used
▶ Clock Running
Status: Entered
Jun 18 → Jun 18, 2026
0 business days (counted)
Running total: 25 of ? biz days used
▶ Clock Running
Status: Assigned
Jun 18 → Jun 18, 2026
0 business days (counted)
Running total: 25 of ? biz days used
▶ Clock Running
Status: Scheduled
Jun 18 → Jun 18, 2026
0 business days (counted)
Running total: 25 of ? biz days used
▶ Clock Running
Status: Entered
Jun 18 → Jun 18, 2026
0 business days (counted)
Running total: 25 of ? biz days used
▶ Clock Running
Status: Assigned
Jun 18 → Jun 18, 2026
0 business days (counted)
Running total: 25 of ? biz days used
▶ Clock Running
Status: Scheduled
Jun 18 → Jun 19, 2026
0 business days (counted)
Running total: 25 of ? biz days used
▶ Clock Running
Status: Entered
Jun 19 → Jun 19, 2026
0 business days (counted)
Running total: 25 of ? biz days used
⏸ Clock Paused
Status: Ready for Release
Jun 19 → Jul 1, 2026
8 business days (not counted)
▶ Clock Running
Status: Assigned
Jul 1 → Jul 1, 2026
0 business days (counted)
Running total: 25 of ? biz days used
▶ Clock Running
Status: Scheduled
Jul 1 → Jul 2, 2026
1 business day (counted)
Running total: 26 of ? biz days used
Created: Jan 6, 2026 Completed: Jul 2, 2026
Show SLA Clock Detail (34 periods)
Period Status Clock Biz Days Running Total
Jan 6 → Jan 7 Created ▶ Running 1 1
Jan 7 → Mar 4 Ready for Release ⏸ Paused 38
Mar 4 → Mar 4 Assigned ▶ Running 0 1
Mar 4 → Mar 16 Scheduled ▶ Running 8 9
Mar 16 → Mar 31 Reschedule ▶ Running 11 20
Mar 31 → Mar 31 Entered ▶ Running 0 20
Mar 31 → Apr 29 Ready for Release ⏸ Paused 21
Apr 29 → Apr 29 Assigned ▶ Running 0 20
Apr 29 → May 1 Scheduled ▶ Running 2 22
May 1 → May 1 Entered ▶ Running 0 22
May 1 → May 6 Ready for Release ⏸ Paused 3
May 6 → May 6 Assigned ▶ Running 0 22
May 6 → May 6 Entered ▶ Running 0 22
May 6 → May 13 Ready for Release ⏸ Paused 5
May 13 → May 13 Assigned ▶ Running 0 22
May 13 → May 15 Scheduled ▶ Running 2 24
May 15 → May 15 Entered ▶ Running 0 24
May 15 → May 21 Ready for Release ⏸ Paused 4
May 21 → May 21 Assigned ▶ Running 0 24
May 21 → May 22 Scheduled ▶ Running 1 25
May 22 → May 22 Entered ▶ Running 0 25
May 22 → Jun 18 Ready for Release ⏸ Paused 18
Jun 18 → Jun 18 Assigned ▶ Running 0 25
Jun 18 → Jun 18 Scheduled ▶ Running 0 25
Jun 18 → Jun 18 Entered ▶ Running 0 25
Jun 18 → Jun 18 Assigned ▶ Running 0 25
Jun 18 → Jun 18 Scheduled ▶ Running 0 25
Jun 18 → Jun 18 Entered ▶ Running 0 25
Jun 18 → Jun 18 Assigned ▶ Running 0 25
Jun 18 → Jun 19 Scheduled ▶ Running 0 25
Jun 19 → Jun 19 Entered ▶ Running 0 25
Jun 19 → Jul 1 Ready for Release ⏸ Paused 8
Jul 1 → Jul 1 Assigned ▶ Running 0 25
Jul 1 → Jul 2 Scheduled ▶ Running 1 26
Holding 103.7d (excluded)
Coordinators 30.8d
Field Work 0.0d
Billing 2.0d
✗ SLA Missed
Holding (excluded from total)
103.7 days
Coordinators
30.8 days
Over SLA
Field Work
0.0 days
Billing
2.0 days
Over SLA
Created: Jan 6, 2026 Due: Dec 31, 2026 Completed: Jul 2, 2026 (182 days early)
📅
123.0 days Total Age
⏱️
39.0d in Ready for Release Longest Stage
🔄
23 transitions Status Changes
⚠️
19.2d over Total Delay
📦
0 orders, 0 quotes Parts & Quotes
📝
5 lines Work Details
🏠
1 visit On-Site Trips
📋
Coordinator Scheduling

AI Analysis

Powered by OpenAI
Generating AI analysis...
Completed with significant delays
Invoiced • 220 days old
🚨
Primary Delay 39.0 days stuck in "Ready for Release"
⏱️
Total Delay 19.2 business days over SLA thresholds

SLA vs Actual Time by Status

Actual (within SLA)
Actual (over SLA)
SLA Target
On Hold
1.6d
Ready for Release
102.1d
Scheduled
19.5d / 2.0d SLA
Reschedule
11.2d / 2.0d SLA
Assigned
0.0d / 0.5d SLA
Completed
0.0d / 1.0d SLA
Closed
1.0d / 1.0d SLA
Ready to Bill
2.0d / 1.0d SLA
Invoice Pending
0.0d / 2.0d SLA

💬 Activities, Notes & Communications

🔧 Work Performed
7/1 CLacy- PM Service completed to manufacture specs. Functional testing passed. This unit is in proper working condition and is ready to return to service
🔍 Technician Findings
PM Service is due
⚠️ Problem Description
Please Perform a PM on this Kiosk and attach all required photos from Checklist Regardless if a PM was completed or not a Checklist and photos are required as well as a signed field service report for every work order If a follow up is needed: Confirm with Tech support, select New issue, enter in the troubleshooting performed and part needed for the follow up in the follow up notes field Trunk stock work order: email dispatch@emsar.com with current work order # and the description of the repair that is required to be performed prior to PM completion (Example LED lights, bamboo seat replacement, Leveler replacement etc. all parts that can be found in your trunk stock ) Link to Work Instructions & Checklist on last page: SZZT (Higi Green) https://emsar-portal1.sharepoint.com/SOPs%20and%20Work%20Instructions/Higi%20&%20Legacy%20Kiosk%20Group/Higi%20Green/WI-ST-310%20Higi%20Green%20Preventative%20Maintenance%20009%20DCR652.pdf
📄 Description
Higi Station with 3G installed

Timeline

📋
Work Order Created Jan 6, 2:13 PM
Work Order: WO-01329886
Type: Preventive Maintenance
Priority: PSM
Status: Ready for Release by Stephanie Ramen Jan 7, 10:03 AM
From: On Hold
To: Ready for Release
Duration in Previous: 19h 49m
🚨 39.0 business days
👷
3 Technician Assigned Mar 4, 11:11 AM
Technician Assigned → Status: Assigned → Dispatch Scheduled
👷
Status: Assigned by Kaitlyn Kelch
From: Ready for Release, Assigned
To: Assigned, Scheduled
Duration in Previous: 56d 1h, 0m
📅
Dispatch Scheduled by Kaitlyn Kelch
Scheduled For: 2026-03-10T14:00:00.000+0000
2.0 business days
📅
Dispatch Scheduled by Kaitlyn Kelch Mar 5, 4:13 PM
Scheduled For: 2026-03-13T14:00:00.000+0000
3.0 business days
📅
Dispatch Scheduled by Kaitlyn Kelch Mar 9, 9:13 AM
Scheduled For: 2026-03-27T14:00:00.000+0000
⚠️ 6.0 business days
🔄
Status: Reschedule by Kaitlyn Kelch Mar 16, 10:00 AM
From: Scheduled
To: Reschedule
Duration in Previous: 11d 21h
🚨 11.0 business days
🆕
Status: Entered by Rhea Berry Mar 30, 9:57 PM
From: Reschedule, Entered
To: Entered, Ready for Release
Duration in Previous: 14d 11h, 0m
🚨 22.3 business days
👷
4 Technician Assigned Apr 29, 11:40 AM
Technician Assigned → Status: Assigned → Dispatch Scheduled → Status: Scheduled
👷
Status: Assigned by Kaitlyn Kelch
From: Ready for Release
To: Assigned
Duration in Previous: 29d 13h
📅
Dispatch Scheduled by Kaitlyn Kelch
Scheduled For: 2026-05-05T17:30:00.000+0000, 2026-05-05T16:30:00.000+0000
🗓️
Status: Scheduled by Kaitlyn Kelch
From: Assigned
To: Scheduled
Duration in Previous: 4m
2.0 business days
📅
Dispatch Scheduled by Kaitlyn Kelch Apr 30, 2:36 PM
Scheduled For: 2026-05-08T14:00:00.000+0000
🆕
Status: Entered by Kaitlyn Kelch May 1, 2:03 PM
From: Scheduled, Entered
To: Entered, Ready for Release
Duration in Previous: 2d 2h, 0m
4.0 business days
👷
2 Technician Assigned May 6, 9:03 AM
Technician Assigned → Status: Assigned
👷
Status: Assigned by Kaitlyn Kelch
From: Ready for Release
To: Assigned
Duration in Previous: 4d 19h
🆕
Status: Entered by Kaitlyn Kelch May 6, 9:17 AM
From: Assigned, Entered
To: Entered, Ready for Release
Duration in Previous: 13m, 0m
⚠️ 6.0 business days
👷
3 Technician Assigned May 13, 10:15 AM
Technician Assigned → Status: Assigned → Dispatch Scheduled
👷
Status: Assigned by Kaitlyn Kelch
From: Ready for Release, Assigned
To: Assigned, Scheduled
Duration in Previous: 7d 0h, 0m
📅
Dispatch Scheduled by Kaitlyn Kelch
Scheduled For: 2026-05-19T16:30:00.000+0000
3.0 business days
🆕
Status: Entered by Kaitlyn Kelch May 15, 9:05 AM
From: Scheduled, Entered
To: Entered, Ready for Release
Duration in Previous: 1d 22h, 0m
⚠️ 5.0 business days
👷
3 Technician Assigned May 21, 10:39 AM
Technician Assigned → Status: Assigned → Dispatch Scheduled
👷
Status: Assigned by Kaitlyn Kelch
From: Ready for Release, Assigned
To: Assigned, Scheduled
Duration in Previous: 6d 1h, 0m
📅
Dispatch Scheduled by Kaitlyn Kelch
Scheduled For: 2026-05-27T14:00:00.000+0000
📅
Dispatch Scheduled by Kaitlyn Kelch May 21, 1:57 PM
Scheduled For: 2026-05-29T14:00:00.000+0000
🆕
Status: Entered by Kaitlyn Kelch May 22, 12:18 PM
From: Scheduled, Entered
To: Entered, Ready for Release
Duration in Previous: 1d 1h, 0m
🚨 19.0 business days
👷
6 Technician Assigned Jun 18, 11:00 AM
Technician Assigned → Status: Assigned → Dispatch Scheduled → Status: Entered → Technician Assigned → Dispatch Scheduled
👷
Status: Assigned by Kaitlyn Kelch
From: Ready for Release, Assigned
To: Assigned, Scheduled
Duration in Previous: 26d 22h, 0m
📅
Dispatch Scheduled by Kaitlyn Kelch
Scheduled For: 2026-06-23T15:00:00.000+0000
🆕
Status: Entered by Kaitlyn Kelch
From: Scheduled, Entered, Assigned
To: Entered, Assigned, Scheduled
Duration in Previous: 1m, 0m
👷
Technician Assigned by Kaitlyn Kelch
Technician: Christopher Womack
📅
Dispatch Scheduled by Kaitlyn Kelch
Scheduled For: 2026-06-23T15:00:00.000+0000
🆕
3 Status: Entered Jun 18, 3:37 PM
Status: Entered → Technician Assigned → Dispatch Scheduled
👷
Technician Assigned by Kaitlyn Kelch
Technician: a0h5A00000HFAYSQA5, Chane Lacy
📅
Dispatch Scheduled by Kaitlyn Kelch
Scheduled For: 2026-06-23T14:00:00.000+0000, 2026-06-23T17:00:00.000+0000
🆕
Status: Entered by Kaitlyn Kelch Jun 19, 1:40 PM
From: Scheduled, Entered
To: Entered, Ready for Release
Duration in Previous: 22h 2m, 0m
⚠️ 7.0 business days
👷
4 Status: Assigned Jun 30, 11:11 PM
Status: Assigned → Technician Assigned → Dispatch Scheduled → Dispatch Scheduled
👷
Technician Assigned by Rhea Berry
Technician: Chane Lacy
📅
Dispatch Scheduled by Rhea Berry
Scheduled For: 2026-07-01T18:30:00.000+0000
📅
Dispatch Scheduled by Rhea Berry
Scheduled For: 2026-07-01T20:30:00.000+0000, 2026-07-01T19:30:00.000+0000
1.1 business days
⏱️
3 5x Labor Added Jul 1, 11:27 PM
5x Labor Added → Status: Completed → Status: Closed
✔️
Status: Completed by Chane Lacy
From: Scheduled
To: Completed
Duration in Previous: 1d 0h
🏁
Status: Closed by Chane Lacy
From: Completed
To: Closed
Duration in Previous: 3m
📄
Status: Ready to Bill by Timothy Amburgey Jul 2, 11:42 AM
From: Closed
To: Ready to Bill
Duration in Previous: 12h 11m
2.0 business days
📨
Status: Invoice Pending by Hannah Shaw Jul 6, 4:04 PM
From: Ready to Bill
To: Invoice Pending
Duration in Previous: 4d 4h
💰
Status: Invoiced by Hannah Shaw Jul 6, 4:27 PM
From: Invoice Pending
To: Invoiced
Duration in Previous: 23m
🧾
Invoice Created Jul 7, 3:55 PM
Invoice Number: SM-266519

Bottlenecks

Scheduled
Duration: 9.0 business days (threshold: 2.0 business days)
Exceeded by 7.0 business days
Reschedule
Duration: 11.2 business days (threshold: 2.0 business days)
Exceeded by 9.2 business days
Scheduled
Duration: 3.0 business days (threshold: 2.0 business days)
Exceeded by 1.0 business days
Scheduled
Duration: 3.0 business days (threshold: 2.0 business days)
Exceeded by 1.0 business days
Ready to Bill
Duration: 2.0 business days (threshold: 1.0 business days)
Exceeded by 1.0 business days

🔗 Related Artifacts

No related artifacts

ℹ️ Work Order Details

Status
Invoiced
Priority
PSM
Type
Preventive Maintenance
Branch
N/A
Technician
Chane Lacy
Scheduled
Jul 1, 3:30 PM
Created
Jan 6, 2:13 PM
Invoice #
SM-266519

Work Details (5)

Name Type Status Qty Amount Date
WL-03281635 Labor Open 0.5 $0.00 Jul 1, 11:27 PM
WL-03281636 Labor Open 0.75 $0.00 Jul 1, 11:27 PM
WL-03281637 Labor Open 1.75 $0.00 Jul 1, 11:27 PM
WL-03281638 Travel Open 11 $0.00 Jul 1, 11:27 PM
WL-03281639 Travel Open 86 $0.00 Jul 1, 11:27 PM

Details