📍 Sam's Club #8296 — 3660 East Sunshine Street, Springfield MO, 65809
Jan 6, 2026 → Oct 6, 2026
🔴 Behind
PSM
SLA Clock
Last business day of January 2026 · Target: Jan 30, 2026
✗ SLA Missed (25 biz days late)
Active: 43 biz days
Paused: 146 biz days
🕐 Clock stopped: Completed (Oct 6, 2026)
▶ Clock Running
Status: Created
Jan 6 → Jan 7, 2026
1 business day (counted)
Running total: 1 of ? biz days used
⏸ Clock Paused
Status: Ready for Release
Jan 7 → Jan 14, 2026
5 business days (not counted)
▶ Clock Running
Status: Assigned
Jan 14 → Jan 14, 2026
0 business days (counted)
Running total: 1 of ? biz days used
▶ Clock Running
Status: Scheduled
Jan 14 → Jan 28, 2026
9 business days (counted)
Running total: 10 of ? biz days used
▶ Clock Running
Status: Reschedule
Jan 28 → Feb 4, 2026
5 business days (counted)
Running total: 15 of ? biz days used
▶ Clock Running
Status: Entered
Feb 4 → Feb 4, 2026
0 business days (counted)
Running total: 15 of ? biz days used
⏸74d
⏸ Clock Paused
Status: Ready for Release
Feb 4 → May 20, 2026
74 business days (not counted)
▶ Clock Running
Status: Assigned
May 20 → May 20, 2026
0 business days (counted)
Running total: 15 of ? biz days used
▶ Clock Running
Status: Scheduled
May 20 → May 28, 2026
5 business days (counted)
Running total: 20 of ? biz days used
▶ Clock Running
Status: Entered
May 28 → May 28, 2026
0 business days (counted)
Running total: 20 of ? biz days used
⏸67d
⏸ Clock Paused
Status: Ready for Release
May 28 → Sep 2, 2026
67 business days (not counted)
▶ Clock Running
Status: Ready for Scheduling
Sep 2 → Sep 3, 2026
1 business day (counted)
Running total: 21 of ? biz days used
▶ Clock Running
Status: Assigned
Sep 3 → Sep 3, 2026
0 business days (counted)
Running total: 21 of ? biz days used
22d
▶ Clock Running
Status: Scheduled
Sep 3 → Oct 6, 2026
22 business days (counted)
Running total: 43 of ? biz days used
▶ Clock Running
Status: Tech On Site
Oct 6 → Oct 6, 2026
0 business days (counted)
Running total: 43 of ? biz days used
Created: Jan 6, 2026Completed: Oct 6, 2026
Show SLA Clock Detail (15 periods)
Period
Status
Clock
Biz Days
Running Total
Jan 6 → Jan 7
Created
▶ Running
1
1
Jan 7 → Jan 14
Ready for Release
⏸ Paused
5
—
Jan 14 → Jan 14
Assigned
▶ Running
0
1
Jan 14 → Jan 28
Scheduled
▶ Running
9
10
Jan 28 → Feb 4
Reschedule
▶ Running
5
15
Feb 4 → Feb 4
Entered
▶ Running
0
15
Feb 4 → May 20
Ready for Release
⏸ Paused
74
—
May 20 → May 20
Assigned
▶ Running
0
15
May 20 → May 28
Scheduled
▶ Running
5
20
May 28 → May 28
Entered
▶ Running
0
20
May 28 → Sep 2
Ready for Release
⏸ Paused
67
—
Sep 2 → Sep 3
Ready for Scheduling
▶ Running
1
21
Sep 3 → Sep 3
Assigned
▶ Running
0
21
Sep 3 → Oct 6
Scheduled
▶ Running
22
43
Oct 6 → Oct 6
Tech On Site
▶ Running
0
43
Holding149.9d (excluded)
Coordinators45.8d
Field Work0.4d
Billing2.0d
✗ SLA Missed
Holding(excluded from total)
149.9 days
Coordinators
45.8 days
Over SLA
Field Work
0.4 days
Billing
2.0 days
Created: Jan 6, 2026
Due: Dec 31, 2026 (70 days left)
📅
189.6 daysTotal Age
⏱️
74.3d in Ready for ReleaseLongest Stage
🔄
14 transitionsStatus Changes
⚠️
37.8d overTotal Delay
📦
0 orders, 0 quotesParts & Quotes
📝
3 linesWork Details
🏠
1 visitOn-Site Trips
👤
Self-ScheduledScheduling
AI Analysis
Powered by OpenAI
Generating AI analysis...
Behind Schedule - Needs Attention
Billing Review • 289 days old
🚨
Primary Delay74.3 days stuck in "Ready for Release"
⏱️
Total Delay37.8 business days over SLA thresholds
SLA vs Actual Time by Status
Actual (within SLA)
Actual (over SLA)
SLA Target
On Hold
1.6d
Ready for Release
148.3d
Scheduled
38.5d / 2.0d SLA
Reschedule
5.5d / 2.0d SLA
Ready for Scheduling
1.8d / 1.0d SLA
Assigned
0.0d / 0.5d SLA
Tech On Site
0.4d / 1.0d SLA
Closed
3.1d / 1.0d SLA
WO Correction Needed
2.0d
💬 Activities, Notes & Communications
🔒Internal CSA Notes
10.7.26 hshaw - please re-attached FSR form version 4
🔧Work Performed
I arrived on location to perform pm I then open cabinet and placed black box on the unit and then placed keyboard and mouse to unit and enter system. Went through the pm procedures and ensuring sound worked. Unit did pass test. I then checked seat for weight and unit passed all test. I then calibrated the screen. I then blew out cabinet and cleaned and disinfected machine. Place pm sticker on unit. I got signature from point of contact and placed the unit back in service
🔍Technician Findings
Kiosk was fully operational
⚠️Problem Description
Please Perform a PM on this Kiosk and attach all required photos from Checklist Regardless if a PM was completed or not a Checklist and photos are required as well as a signed field service report for every work order If a follow up is needed: Confirm with Tech support, select New issue, enter in the troubleshooting performed and part needed for the follow up in the follow up notes field Trunk stock work order: email dispatch@emsar.com with current work order # and the description of the repair that is required to be performed prior to PM completion (Example LED lights, bamboo seat replacement, Leveler replacement etc. all parts that can be found in your trunk stock ) Link to Work Instructions & Checklist on last page: SZZT (Higi Green) https://emsar-portal1.sharepoint.com/SOPs%20and%20Work%20Instructions/Higi%20&%20Legacy%20Kiosk%20Group/Higi%20Green/WI-ST-310%20Higi%20Green%20Preventative%20Maintenance%20009%20DCR652.pdf
📄Description
Higi Green Kiosk with 4G installed
Oct 9, 2026 11:46am
@Darrell Hendrix PM checklist has no issue. QC Team requires FSR form version# 4. @Craig Dempsey would you please assist with the FSR form matter? Thank you
📅
WO-01330070 - Preventive Maintenance - DD: 12/31/2026 - - ZT2776-4G - Springfield - Sam's Club #8296
Oct 6, 2026 10:00am – 11:00am
Work Order: WO-01330070
Account: HIGI LLC
Customer Case Number:
Location: Sam's Club #8296
Address: 3660 East Sunshine Street, Springfield, MO 65809
Manufacturer: Higi
Model #: ZT2776-4G
Serial #: CSA-2016014988
Contact Name:
Contact Phone:
Contact Email:
Due Date: 12/31/2026
Scheduled Date/Time