📍 Sam's Club #4878 — 5 ILLINI DR, Glen Carbon IL, 62034
Jan 6, 2026 → Apr 21, 2026
✅ Completed
PSM
SLA Clock
Last business day of January 2026 · Target: Jan 30, 2026
✗ SLA Missed (17 biz days late)
Active: 35 biz days
Paused: 37 biz days
🕐 Clock stopped: Tech Off Site (Apr 20, 2026)
▶ Clock Running
Status: Created
Jan 6 → Jan 7, 2026
1 business day (counted)
Running total: 1 of ? biz days used
⏸ Clock Paused
Status: Ready for Release
Jan 7 → Jan 8, 2026
1 business day (not counted)
▶ Clock Running
Status: Assigned
Jan 8 → Jan 8, 2026
0 business days (counted)
Running total: 1 of ? biz days used
29d
▶ Clock Running
Status: Scheduled
Jan 8 → Feb 20, 2026
29 business days (counted)
Running total: 30 of ? biz days used
▶ Clock Running
Status: Reschedule
Feb 20 → Feb 22, 2026
0 business days (counted)
Running total: 30 of ? biz days used
▶ Clock Running
Status: Entered
Feb 22 → Feb 22, 2026
0 business days (counted)
Running total: 30 of ? biz days used
⏸36d
⏸ Clock Paused
Status: Ready for Release
Feb 22 → Apr 13, 2026
36 business days (not counted)
▶ Clock Running
Status: Assigned
Apr 13 → Apr 13, 2026
0 business days (counted)
Running total: 30 of ? biz days used
▶ Clock Running
Status: Scheduled
Apr 13 → Apr 20, 2026
5 business days (counted)
Running total: 35 of ? biz days used
▶ Clock Running
Status: Tech On Site
Apr 20 → Apr 20, 2026
0 business days (counted)
Running total: 35 of ? biz days used
Created: Jan 6, 2026Tech Off Site: Apr 20, 2026
Show SLA Clock Detail (10 periods)
Period
Status
Clock
Biz Days
Running Total
Jan 6 → Jan 7
Created
▶ Running
1
1
Jan 7 → Jan 8
Ready for Release
⏸ Paused
1
—
Jan 8 → Jan 8
Assigned
▶ Running
0
1
Jan 8 → Feb 20
Scheduled
▶ Running
29
30
Feb 20 → Feb 22
Reschedule
▶ Running
0
30
Feb 22 → Feb 22
Entered
▶ Running
0
30
Feb 22 → Apr 13
Ready for Release
⏸ Paused
36
—
Apr 13 → Apr 13
Assigned
▶ Running
0
30
Apr 13 → Apr 20
Scheduled
▶ Running
5
35
Apr 20 → Apr 20
Tech On Site
▶ Running
0
35
Holding39.6d (excluded)
Coordinators37.0d
Field Work2.0d
Billing0.0d
✗ SLA Missed
Holding(excluded from total)
39.6 days
Coordinators
37.0 days
Over SLA
Field Work
2.0 days
Billing
0.0 days
Created: Jan 6, 2026
Due: Dec 31, 2026
Completed: Apr 21, 2026 (254 days early)
📅
73.6 daysTotal Age
⏱️
36.0d in Ready for ReleaseLongest Stage
🔄
12 transitionsStatus Changes
⚠️
32.3d overTotal Delay
📦
0 orders, 0 quotesParts & Quotes
📝
3 linesWork Details
🏠
1 visitOn-Site Trips
👤
Self-ScheduledScheduling
AI Analysis
Powered by OpenAI
Generating AI analysis...
Completed with significant delays
Invoiced • 220 days old
🚨
Primary Delay36.0 days stuck in "Ready for Release"
⏱️
Total Delay32.3 business days over SLA thresholds
SLA vs Actual Time by Status
Actual (within SLA)
Actual (over SLA)
SLA Target
On Hold
1.6d
Ready for Release
38.0d
Assigned
0.0d / 0.5d SLA
Scheduled
36.0d / 2.0d SLA
Reschedule
1.0d / 2.0d SLA
Tech On Site
0.1d / 1.0d SLA
Tech Off Site
1.9d / 2.0d SLA
Closed
1.3d / 1.0d SLA
Ready to Bill
0.0d / 1.0d SLA
Invoice Pending
0.0d / 2.0d SLA
💬 Activities, Notes & Communications
🔒Internal CSA Notes
4/21/26 CDempsey- Kevin cannot complete wo due to linked work instructions and checklist not working. Reached out to Dispatch.
2/21/26 RBerry- Found WO in reschedule status. Cleared tech and placed WO back into RFR. Removed delay code.
🔧Work Performed
Pm completed
🔍Technician Findings
No issue found
⚠️Problem Description
Please Perform a PM on this Kiosk and attach all required photos from Checklist Regardless if a PM was completed or not a Checklist and photos are required as well as a signed field service report for every work order If a follow up is needed: Confirm with Tech support, select New issue, enter in the troubleshooting performed and part needed for the follow up in the follow up notes field Trunk stock work order: email dispatch@emsar.com with current work order # and the description of the repair that is required to be performed prior to PM completion (Example LED lights, bamboo seat replacement, Leveler replacement etc. all parts that can be found in your trunk stock ) Link to Work Instructions & Checklist on last page: SZZT (Higi Green) https://emsar-portal1.sharepoint.com/SOPs%20and%20Work%20Instructions/Higi%20&%20Legacy%20Kiosk%20Group/Higi%20Green/WI-ST-310%20Higi%20Green%20Preventative%20Maintenance%20009%20DCR652.pdf