📍 Publix 840 — 10015 N Dale Mabry Hwy, Tampa FL, 33618
Jan 6, 2026 → Oct 19, 2026
✅ Completed
PSM
SLA Clock
Last business day of January 2026 · Target: Jan 30, 2026
✗ SLA Missed (14 biz days late)
Active: 32 biz days
Paused: 165 biz days
🕐 Clock stopped: Completed (Oct 19, 2026)
▶ Clock Running
Status: Created
Jan 6 → Jan 7, 2026
1 business day (counted)
Running total: 1 of ? biz days used
⏸165d
⏸ Clock Paused
Status: Ready for Release
Jan 7 → Sep 2, 2026
165 business days (not counted)
30d
▶ Clock Running
Status: Ready for Scheduling
Sep 2 → Oct 16, 2026
30 business days (counted)
Running total: 31 of ? biz days used
▶ Clock Running
Status: Assigned
Oct 16 → Oct 16, 2026
0 business days (counted)
Running total: 31 of ? biz days used
▶ Clock Running
Status: Scheduled
Oct 16 → Oct 19, 2026
1 business day (counted)
Running total: 32 of ? biz days used
▶ Clock Running
Status: Tech On Site
Oct 19 → Oct 19, 2026
0 business days (counted)
Running total: 32 of ? biz days used
▶ Clock Running
Status: Completed
Oct 19 → Oct 19, 2026
0 business days (counted)
Running total: 32 of ? biz days used
▶ Clock Running
Status: Incomplete
Oct 19 → Oct 19, 2026
0 business days (counted)
Running total: 32 of ? biz days used
Created: Jan 6, 2026Completed: Oct 19, 2026
Show SLA Clock Detail (8 periods)
Period
Status
Clock
Biz Days
Running Total
Jan 6 → Jan 7
Created
▶ Running
1
1
Jan 7 → Sep 2
Ready for Release
⏸ Paused
165
—
Sep 2 → Oct 16
Ready for Scheduling
▶ Running
30
31
Oct 16 → Oct 16
Assigned
▶ Running
0
31
Oct 16 → Oct 19
Scheduled
▶ Running
1
32
Oct 19 → Oct 19
Tech On Site
▶ Running
0
32
Oct 19 → Oct 19
Completed
▶ Running
0
32
Oct 19 → Oct 19
Incomplete
▶ Running
0
32
Holding167.6d (excluded)
Coordinators32.2d
Field Work0.2d
Billing1.3d
✗ SLA Missed
Holding(excluded from total)
167.6 days
Coordinators
32.2 days
Over SLA
Field Work
0.2 days
Billing
1.3 days
Over SLA
Created: Jan 6, 2026
Due: Dec 31, 2026
Completed: Oct 19, 2026 (73 days early)
📅
197.6 daysTotal Age
⏱️
166.0d in Ready for ReleaseLongest Stage
🔄
11 transitionsStatus Changes
⚠️
30.7d overTotal Delay
📦
0 orders, 0 quotesParts & Quotes
📝
4 linesWork Details
🏠
1 visitOn-Site Trips
👤
Self-ScheduledScheduling
AI Analysis
Powered by OpenAI
Generating AI analysis...
Completed with significant delays
Invoiced • 289 days old
🚨
Primary Delay166.0 days stuck in "Ready for Release"
⏱️
Total Delay30.7 business days over SLA thresholds
SLA vs Actual Time by Status
Actual (within SLA)
Actual (over SLA)
SLA Target
On Hold
1.6d
Ready for Release
166.0d
Ready for Scheduling
30.8d / 1.0d SLA
Assigned
0.0d / 0.5d SLA
Scheduled
1.5d / 2.0d SLA
Tech On Site
0.1d / 1.0d SLA
Completed
0.1d / 1.0d SLA
Closed
1.7d / 1.0d SLA
Ready to Bill
1.3d / 1.0d SLA
Invoice Pending
0.0d / 2.0d SLA
💬 Activities, Notes & Communications
🔧Work Performed
The kiosk failed the pressure test and is missing a leveler.
🔍Technician Findings
The kiosk was functioning normally.
⚠️Problem Description
Please Perform a PM on this Kiosk and attach all required photos from Checklist Regardless if a PM was completed or not a Checklist and photos are required as well as a signed field service report for every work order If a follow up is needed: Confirm with Tech support, select New issue, enter in the troubleshooting performed and part needed for the follow up in the follow up notes field Trunk stock work order: email dispatch@emsar.com with current work order # and the description of the repair that is required to be performed prior to PM completion (Example LED lights, bamboo seat replacement, Leveler replacement etc. all parts that can be found in your trunk stock ) Link to Work Instructions & Checklist on last page: SZZT (Higi Green) https://emsar-portal1.sharepoint.com/SOPs%20and%20Work%20Instructions/Higi%20&%20Legacy%20Kiosk%20Group/Higi%20Green/WI-ST-310%20Higi%20Green%20Preventative%20Maintenance%20009%20DCR652.pdf