📍 Sam's Club #4992 — 1500 Ring Road, Elizabethtown KY, 42701
Jan 6, 2026 → Oct 14, 2026
✅ Completed
PSM
SLA Clock
Last business day of January 2026 · Target: Jan 30, 2026
✗ SLA Missed (11 biz days late)
Active: 29 biz days
Paused: 165 biz days
🕐 Clock stopped: Tech Off Site (Oct 14, 2026)
▶ Clock Running
Status: Created
Jan 6 → Jan 7, 2026
1 business day (counted)
Running total: 1 of ? biz days used
⏸165d
⏸ Clock Paused
Status: Ready for Release
Jan 7 → Sep 2, 2026
165 business days (not counted)
17d
▶ Clock Running
Status: Ready for Scheduling
Sep 2 → Sep 28, 2026
17 business days (counted)
Running total: 18 of ? biz days used
▶ Clock Running
Status: Assigned
Sep 28 → Oct 7, 2026
7 business days (counted)
Running total: 25 of ? biz days used
▶ Clock Running
Status: Scheduled
Oct 7 → Oct 14, 2026
4 business days (counted)
Running total: 29 of ? biz days used
▶ Clock Running
Status: Tech On Site
Oct 14 → Oct 14, 2026
0 business days (counted)
Running total: 29 of ? biz days used
Created: Jan 6, 2026Tech Off Site: Oct 14, 2026
Show SLA Clock Detail (6 periods)
Period
Status
Clock
Biz Days
Running Total
Jan 6 → Jan 7
Created
▶ Running
1
1
Jan 7 → Sep 2
Ready for Release
⏸ Paused
165
—
Sep 2 → Sep 28
Ready for Scheduling
▶ Running
17
18
Sep 28 → Oct 7
Assigned
▶ Running
7
25
Oct 7 → Oct 14
Scheduled
▶ Running
4
29
Oct 14 → Oct 14
Tech On Site
▶ Running
0
29
Holding167.6d (excluded)
Coordinators29.8d
Field Work0.9d
Billing1.0d
✗ SLA Missed
Holding(excluded from total)
167.6 days
Coordinators
29.8 days
Over SLA
Field Work
0.9 days
Billing
1.0 days
Created: Jan 6, 2026
Due: Dec 31, 2026
Completed: Oct 15, 2026 (77 days early)
📅
195.0 daysTotal Age
⏱️
166.0d in Ready for ReleaseLongest Stage
🔄
9 transitionsStatus Changes
⚠️
27.3d overTotal Delay
📦
0 orders, 0 quotesParts & Quotes
📝
3 linesWork Details
🏠
1 visitOn-Site Trips
👤
Self-ScheduledScheduling
AI Analysis
Powered by OpenAI
Generating AI analysis...
Completed with significant delays
Invoiced • 289 days old
🚨
Primary Delay166.0 days stuck in "Ready for Release"
⏱️
Total Delay27.3 business days over SLA thresholds
SLA vs Actual Time by Status
Actual (within SLA)
Actual (over SLA)
SLA Target
On Hold
1.6d
Ready for Release
166.0d
Ready for Scheduling
17.8d / 1.0d SLA
Assigned
7.4d / 0.5d SLA
Scheduled
4.6d / 2.0d SLA
Tech Off Site
0.9d / 2.0d SLA
Completed
0.0d / 1.0d SLA
Closed
2.0d / 1.0d SLA
Ready to Bill
1.0d / 1.0d SLA
💬 Activities, Notes & Communications
🔧Work Performed
PM completed
🔍Technician Findings
Unit in service
⚠️Problem Description
Please Perform a PM on this Kiosk and attach all required photos from Checklist Regardless if a PM was completed or not a Checklist and photos are required as well as a signed field service report for every work order If a follow up is needed: Confirm with Tech support, select New issue, enter in the troubleshooting performed and part needed for the follow up in the follow up notes field Trunk stock work order: email dispatch@emsar.com with current work order # and the description of the repair that is required to be performed prior to PM completion (Example LED lights, bamboo seat replacement, Leveler replacement etc. all parts that can be found in your trunk stock ) Link to Work Instructions & Checklist on last page: SZZT (Higi Green) https://emsar-portal1.sharepoint.com/SOPs%20and%20Work%20Instructions/Higi%20&%20Legacy%20Kiosk%20Group/Higi%20Green/WI-ST-310%20Higi%20Green%20Preventative%20Maintenance%20009%20DCR652.pdf
Work Order: WO-01330928
Account: HIGI LLC
Customer Case Number:
Location: Sam's Club #4992
Address: 1500 Ring Road, Elizabethtown, KY 42701
Manufacturer: Higi
Model #: ZT2776-4G
Serial #: CSA-2016105681
Contact Name:
Contact Phone:
Contact Email:
Due Date: 12/31/2026
Scheduled Date/Time: 2026-10