4 business days from creation · Target: Jan 27, 2026
✗ SLA Missed
Active: 3 biz days
Paused: 18 biz days
Budget: 4 biz days
🕐 Clock stopped: Completed (Feb 20, 2026)
SLA Target
▶ Clock Running
Status: Created
Jan 21 → Jan 21, 2026
0 business days (counted)
Running total: 0 of 4 biz days used
▶ Clock Running
Status: L2 Screening
Jan 21 → Jan 22, 2026
1 business day (counted)
Running total: 1 of 4 biz days used
⏸18d
⏸ Clock Paused
Status: Awaiting Parts
Jan 22 → Feb 18, 2026
18 business days (not counted)
▶ Clock Running
Status: Ready for Scheduling
Feb 18 → Feb 18, 2026
0 business days (counted)
Running total: 1 of 4 biz days used
▶ Clock Running
Status: Assigned
Feb 18 → Feb 18, 2026
0 business days (counted)
Running total: 1 of 4 biz days used
▶ Clock Running
Status: Scheduled
Feb 18 → Feb 20, 2026
2 business days (counted)
Running total: 3 of 4 biz days used
Created: Jan 21, 2026Completed: Feb 20, 2026
Business Days Used3 / 4
04d budget
Show SLA Clock Detail (6 periods)
Period
Status
Clock
Biz Days
Running Total
Jan 21 → Jan 21
Created
▶ Running
0
0 / 4
Jan 21 → Jan 22
L2 Screening
▶ Running
1
1 / 4
Jan 22 → Feb 18
Awaiting Parts
⏸ Paused
18
—
Feb 18 → Feb 18
Ready for Scheduling
▶ Running
0
1 / 4
Feb 18 → Feb 18
Assigned
▶ Running
0
1 / 4
Feb 18 → Feb 20
Scheduled
▶ Running
2
3 / 4
Dispatch0.9d
Material Management19.0d
Coordinators2.5d
Field Work0.2d
Billing0.2d
✗ SLA Missed
Dispatch
0.9 days
Material Management
19.0 days
Over SLA
Coordinators
2.5 days
Over SLA
Field Work
0.2 days
Billing
0.2 days
Created: Jan 21, 2026
Due: Jan 27, 2026
Completed: Feb 20, 2026 (23 days late)
📅
21.5 daysTotal Age
⏱️
19.0d in Awaiting PartsLongest Stage
🔄
8 transitionsStatus Changes
⚠️
22.0d overTotal Delay
📦
2 orders, 0 quotesParts & Quotes
📝
6 linesWork Details
🏠
1 visitOn-Site Trips
📋
CoordinatorScheduling
AI Analysis
Powered by OpenAI
Generating AI analysis...
Completed with significant delays
Invoiced • 204 days old
🚨
Primary Delay19.0 days stuck in "Awaiting Parts"
⏱️
Total Delay22.0 business days over SLA thresholds
SLA vs Actual Time by Status
Actual (within SLA)
Actual (over SLA)
SLA Target
Entered
0.3d / 0.5d SLA
L2 Screening
0.6d / 1.0d SLA
Awaiting Parts
19.0d / 3.0d SLA
Ready for Scheduling
0.1d / 1.0d SLA
Scheduled
2.4d / 2.0d SLA
Completed
0.2d / 1.0d SLA
Closed
6.6d / 1.0d SLA
Ready to Bill
0.2d / 1.0d SLA
💬 Activities, Notes & Communications
🔒Internal CSA Notes
updating part request
871-0001-02R OUT OF STOCK RC 1/22/2026
🔧Work Performed
**R&R touchscreen assembly
**After install of touchscreen the unit died right up showing ads on top screen so no need for router to be replaced.
**PM Completed.
**Lightly dusted inside and outside of higi
**Checked and calibrated audio & volume, BP, touch screen and weight bench.
**Wiped down higi with disinfectant cleaner
**Tested for functionality
**Completed full test successfully
**Verified/Changed BIOS setting to “POWER ON”
🔍Technician Findings
Unit OOS
Touchscreen black with no message on it.
⚠️Problem Description
Tech will be shipped replacement Touchscreen nose assembly. Tech will replace all parts shipped, adjust resolution in resolution settings, calibrate, and restore functionality. Touchscreen should be set as main display.
Touchscreen unresponsive
Resolution settings
1440×900 / 60HZ top
800×600 / 60HZ bottom
Tech will be shipped replacement WIFI Router.
Restore connectivity then verify kiosk is online by logging in as a customer and receiving email results back. Take a picture of account being logged in and attach to your Work Order
Tech will be sent Key to Kiosk
Use this password to access the kiosk: *NE*9!9*
If swapping out a PC, you would use: miker0me0g0lfech0
There is a mandatory 4 business day timeline in which to complete this work. If you have questions or require technical support during the service, call 931-284-4999 and follow the prompts to reach the EMSAR Level II Support team for assistance (Support Hours are Monday-Friday from 8:00 AM EST until 8:00 PM EST). Provide the team member with the Work Order number, location, and problem description. At the completion of the service contact the EMSAR Level II Support team so that they can remotely verify that the kiosk is online and operational.
**ALL NON-EMSAR TECHNICIANS: You must check in from the location as soon as you arrive onsite and before you begin working on the kiosk. Call 931-284-4999 and follow the prompts. If there are any questions about the service expectations, use this opportunity to ask the Level II Support team.**
Please Perform a PM on this Kiosk and attach all required photos from Checklist Regardless if a PM was completed or not a Checklist and photos are required as well as a signed field service report for every work order If a follow up is needed: Confirm with Tech support, select New issue, enter in the troubleshooting performed and part needed for the follow up in the follow up notes field Trunk stock work order: email dispatch@emsar.com with current work order # and the description of the repair that is required to be performed prior to PM completion (Example LED lights, bamboo seat replacement, Leveler replacement etc. all parts that can be found in your trunk stock ) Link to Work Instructions & Checklist on last page: SZZT (Higi Green) https://emsar-portal1.sharepoint.com/SOPs%20and%20Work%20Instructions/Higi%20&%20Legacy%20Kiosk%20Group/Higi%20Green/WI-ST-310%20Higi%20Green%20Preventative%20Maintenance.pdf
📄Description
Merge KMY Kiosk
📋
Inbound from +18606528925
Completed Feb 2, 2026
Customer was calling to check on the status.
📋
Outbound to +18606529208
Completed Jan 21, 2026
Spoke to Brent/pharmacy, the touchscreen is dark. They have rebooted. Unit is offline in the portal. Lights are working. They do have a key.
Feb 17, 2026 7:22pm
@Robert Cox @Brendan Chaney i changed this part this can be picked now no longer a ad monitor request its a touch screen. @Emmanuel Morales