Work Order 360 View

Detailed work order timeline, KPIs, and analysis

← WO Overview

WO-01309450 ↗ ServiceMax

Cornell Scott - Hill Health Center Conneticut • Depot • PSM

📍 Cornell Scott - Roberto Clemente (K-8) — 360 Columbus Ave, New Haven CT, 06519

Oct 15, 2025 → Jan 30, 2026

✅ Completed
PSM Last business day of October 2025
Target: Oct 31, 2025
🕐 Clock stopped: Invoiced (Jan 30)
⏸ 68d excluded (parts wait + holding)
✗ SLA Missed (23d late)
Dispatch 0.0d
Material Management 52.0d
Coordinators 31.6d
Field Work 0.1d
Billing 0.0d
✗ SLA Missed
Dispatch
0.0 days
Material Management
52.0 days
Over SLA
Coordinators
31.6 days
Over SLA
Field Work
0.1 days
Billing
0.0 days
Created: Oct 15, 2025 Due: Nov 14, 2025 Completed: Jan 30, 2026 (76 days late)
📅
78.0 days Total Age
⏱️
16.4d in Awaiting Parts Longest Stage
🔄
16 transitions Status Changes
⚠️
66.9d over Total Delay
📦
6 orders, 0 quotes Parts & Quotes
📝
10 lines Work Details
🏠
1 visit On-Site Trips
📋
Coordinator Scheduling

AI Analysis

Powered by OpenAI
Generating AI analysis...

Originating Case

Open in Salesforce →
🎫
Case #00534240
Needs quote
Closed
Q-00030573 Follow up to WO-01304225 Inspection #: 30045 Asset ID: 13236659 Model: Maico Diagnostics - 8100521 Notes: Out of range. Follow-up required. Highest frequencies not audible on Left side Depot Repair - Recertification Reference Standards - Audiometer: ANSI S3.6 (2004) - Ambient Noise: OSHA (1983) - Headphones: ANSI S3.6 (2004) - 2hr depot labor 1x- 8004246 - AUDIO MAICO MA-1 CABLE FOR AUDIOMETER 3x- Shipping @28
Priority
Standard
Origin
Email
Reason
New Case
Contact
Ana Tanko
Owner
Jessica Sells
Created
Oct 9, 2025
Work Orders from this Case (1)
WO-01309450 (current) Invoiced
Depot • Ryan Schwochow
Created: Oct 15, 2025 • Closed: Jan 30, 2026
Completed with significant delays
Invoiced • 211 days old
🚨
Primary Delay 16.4 days stuck in "Awaiting Parts"
⏱️
Total Delay 66.9 business days over SLA thresholds

SLA vs Actual Time by Status

Actual (within SLA)
Actual (over SLA)
SLA Target
Entered
0.0d / 0.5d SLA
Assigned
3.0d / 0.5d SLA
Awaiting Parts
52.0d / 3.0d SLA
Reschedule
28.6d / 2.0d SLA
Tech On Site
0.1d / 1.0d SLA
Completed
0.0d / 1.0d SLA
Closed
2.5d / 1.0d SLA
Invoice Pending
0.0d / 2.0d SLA

💬 Activities, Notes & Communications

🔒 Internal CSA Notes

12/19 SKLEIN - Allan screw stripped out when replacing wires. Will need a replacement set of the DD45 Headphones to complete the repair. Due to already a long wait time, this part will NOT be charged to customer.


10/15/2025jsells

Q-00030573

🔧 Work Performed
Cleaned device externals - Visual Inspection; Passed - Updated Ebt Inventory - Performed Calibration vis - ACS Hardware Platform: EM-2-100, Serial Number: 1023071801- Reference Standards - Audiometer: ANSI S3.6 (2004) - Passed Ambient Noise: OSHA (1983) - Passed Headphones: ANSI S3.6 (2004) - Passed PM Completed Per MFG Specs - Passed
🔍 Technician Findings
Headphones received into depot. Was able to duplicate issue. Was able to pass the hearing test calibration, but was not able to pass the electrical calibration test. Was not able to hear a reading in the test indicating that the issue lies in the headphone cable. Unit was already quoted for a new cable. Ordering new cable and once new cable has been received, will continue testing on audiometer.
⚠️ Problem Description
Q-00030573 - Follow up to WO-01304225 - Inspection #: 30045 - Asset ID: 13236659 Model: Maico Diagnostics - 8100521 Notes: Out of range. Follow-up required. Highest frequencies not audible on Left side Depot Repair - Recertification Reference Standards - Audiometer: ANSI S3.6 (2004) - Ambient Noise: OSHA (1983) - Headphones: ANSI S3.6 (2004) - https://www.ebiotrack.com/workorder.php?wo=68981

Timeline

📞
Case Linked Oct 9, 11:01 AM
Case Number: 00534240
Subject: Needs quote
Status: Closed
⚠️ 5.0 business days
📋
3 Work Order Created Oct 15, 9:42 AM
Work Order Created → Technician Assigned → Status: Assigned
👷
Technician Assigned by Jessica Sells
Technician: Ryan Schwochow
👷
Status: Assigned by Jessica Sells
From: Entered
To: Assigned
Duration in Previous: 0m
3.0 business days
📦
2 Parts Requested Oct 17, 8:20 AM
Parts Requested → Status: Awaiting Parts
📦
Status: Awaiting Parts by Ryan Schwochow
From: Assigned
To: Awaiting Parts
Duration in Previous: 1d 22h
⚠️ 6.0 business days
📦
3 Parts Requested Oct 24, 12:05 PM
Parts Requested → 3x Parts Added → Status: Reschedule
🔩
3x Parts Added
Type: Parts, Expenses
Status: Open
Qty: 1
🔄
Status: Reschedule by Keith Canterbury
From: Awaiting Parts
To: Reschedule
Duration in Previous: 7d 3h
🚨 13.0 business days
📦
2 Parts Requested Nov 11, 10:04 AM
Parts Requested → Status: Awaiting Parts
📦
Status: Awaiting Parts by Ryan Schwochow
From: Reschedule
To: Awaiting Parts
Duration in Previous: 17d 22h
🚨 15.0 business days
💵
2 Expenses Added Dec 1, 1:16 PM
Expenses Added → Status: Reschedule
🔄
Status: Reschedule by Samuel Klein
From: Awaiting Parts
To: Reschedule
Duration in Previous: 20d 3h
📦
3 Parts Requested Dec 1, 2:32 PM
Parts Requested → Status: Awaiting Parts → 2x Labor Added
📦
Status: Awaiting Parts by Samuel Klein
From: Reschedule
To: Awaiting Parts
Duration in Previous: 1h 16m
⏱️
2x Labor Added
Type: Labor
Status: Open
Qty: 1
🚨 15.0 business days
🔩
2 2x Parts Added Dec 19, 2:52 PM
2x Parts Added → Status: Reschedule
🔄
Status: Reschedule by Keith Canterbury
From: Awaiting Parts
To: Reschedule
Duration in Previous: 18d 0h
📦
2 Parts Requested Dec 19, 3:53 PM
Parts Requested → Status: Awaiting Parts
📦
Status: Awaiting Parts by Samuel Klein
From: Reschedule
To: Awaiting Parts
Duration in Previous: 1h 1m
🚨 17.0 business days
🔩
2 Parts Added Jan 12, 10:40 AM
Parts Added → Status: Reschedule
🔄
Status: Reschedule by Keith Canterbury
From: Awaiting Parts
To: Reschedule
Duration in Previous: 23d 18h
🚨 14.0 business days
🔧
Status: Tech On Site by Samuel Klein Jan 29, 3:26 PM
From: Reschedule
To: Tech On Site
Duration in Previous: 17d 4h
✔️
3 Status: Completed Jan 29, 3:58 PM
Status: Completed → Parts Requested → Status: Awaiting Parts
📦
Parts Requested
Order: 00089330
Status: Closed
📦
Status: Awaiting Parts by Samuel Klein
From: Completed
To: Awaiting Parts
Duration in Previous: 1m
💵
2 Expenses Added Jan 29, 4:05 PM
Expenses Added → Status: Reschedule
🔄
Status: Reschedule by Sean Weaver
From: Awaiting Parts
To: Reschedule
Duration in Previous: 6m
🏁
Status: Closed by Ryan Schwochow Jan 30, 3:16 PM
From: Reschedule
To: Closed
Duration in Previous: 23h 10m
3.0 business days
📄
3 Status: Ready to Bill Feb 3, 4:48 PM
Status: Ready to Bill → Status: Invoiced → Invoice Created
💰
Status: Invoiced by Diane Patton
From: Invoice Pending
To: Invoiced
Duration in Previous: 0m
🧾
Invoice Created
Invoice Number: SM-252932

Bottlenecks

Assigned
Duration: 3.0 business days (threshold: 4.0 business hours)
Exceeded by 2.5 business days
Awaiting Parts
Duration: 6.0 business days (threshold: 3.0 business days)
Exceeded by 3.0 business days
Reschedule
Duration: 13.0 business days (threshold: 2.0 business days)
Exceeded by 11.0 business days
Awaiting Parts
Duration: 15.0 business days (threshold: 3.0 business days)
Exceeded by 12.0 business days
Awaiting Parts
Duration: 14.6 business days (threshold: 3.0 business days)
Exceeded by 11.6 business days
Awaiting Parts
Duration: 16.4 business days (threshold: 3.0 business days)
Exceeded by 13.4 business days
Reschedule
Duration: 14.0 business days (threshold: 2.0 business days)
Exceeded by 12.0 business days
Closed
Duration: 2.5 business days (threshold: 1.0 business days)
Exceeded by 1.5 business days

🔗 Related Artifacts

📞
Case 00534240
Closed
📦
Parts Order 00083734
Closed
📦
Parts Order 00084120
Closed
📦
Parts Order 00085072
Closed
📦
Parts Order 00086042
Closed
📦
Parts Order 00087069
Closed
📦
Parts Order 00089330
Closed

ℹ️ Work Order Details

Status
Invoiced
Priority
PSM
Type
Depot
Branch
N/A
Technician
Ryan Schwochow
Scheduled
N/A
Created
Oct 15, 9:42 AM
Invoice #
SM-252932

Work Details (10)

Name Type Status Qty Amount Date
WL-02983038 Parts Open 1 $1.47 Oct 24, 12:05 PM
WL-02983039 Parts Open 1 $0.00 Oct 24, 12:05 PM
WL-02983040 Expenses Open 1 $0.00 Oct 24, 12:05 PM
WL-03022488 Expenses Open 1 $21.61 Dec 1, 1:16 PM
WL-03022588 Labor Open 1 $149.00 Dec 1, 2:37 PM
WL-03022589 Labor Open 1 $149.00 Dec 1, 2:37 PM
WL-03043555 Parts Open 1 $125.00 Dec 19, 2:52 PM
WL-03043556 Expenses Open 1 $57.28 Dec 19, 2:52 PM
WL-03061498 Parts Open 1 $0.00 Jan 12, 10:40 AM
WL-03083704 Expenses Open 1 $22.18 Jan 29, 4:05 PM

Details