Detailed work order timeline, KPIs, and analysis
MIDMARK • Installation • PC
📍 Britton Road Veterinary Clinic — 2826 W Britton Rd, Oklahoma City OK, 73120-4497
Nov 4, 2025 → May 11, 2026
| Period | Status | Clock | Biz Days | Running Total |
|---|---|---|---|---|
| Nov 4 → Nov 4 | Created | ▶ Running | 0 | 0 |
| Nov 4 → Nov 19 | L2 Screening | ▶ Running | 10 | 10 |
| Nov 19 → Nov 19 | Ready for Scheduling | ▶ Running | 0 | 10 |
| Nov 19 → Nov 19 | Assigned | ▶ Running | 0 | 10 |
| Nov 19 → Nov 19 | Scheduled | ▶ Running | 0 | 10 |
| Nov 19 → Apr 6 | Reschedule | ▶ Running | 92 | 102 |
| Apr 6 → May 11 | Scheduled | ▶ Running | 25 | 127 |
| May 11 → May 12 | Tech On Site | ▶ Running | 1 | 128 |
4/22/26 RBerry- Updated due date based on site request.
4/6 KKelch scheduled per logged email from Junior
3/18 KKelch logged email from Justin- I am on-site now, just spoke with OG&E on the ground. Power should be in today, assuming no issues. I will keep you apprised of the install. Thanks for all your patience and understanding of these unique situations!
3/18 KKelch sent Lo an email to see if we are ready to schedule
3/2 KKelch- per Lo, the site MAY be ready by 3/9
2/23 KKelch- per Lo, this site is not ready to be installed yet
1/23 KKelch logged email from Junior letting us know that electricity has been delayed
12/23 KKelch- logged email from Lo letting us know that electricity was delayed until mid to late January
12/23 KKelch sent Stacey an email for scheduling
12/22 KKelch called Lo to schedule for 12/29 between 12 and 2 pm. Left VM.
11/19 KKelch-per Stacey, they would like to hold off on scheduling as this a new build and the building is still under construction
11/19 KKelch called Lo to schedule for 11/26 between 12 and 2 pm. Customer confirmed.
| Name | Type | Status | Qty | Amount | Date |
|---|---|---|---|---|---|
| WL-03222238 | Labor | Open | 1.25 | $0.00 | May 11, 4:58 PM |
| WL-03222239 | Labor | Open | 3.5 | $385.00 | May 11, 4:58 PM |
| WL-03222240 | Travel | Open | 32 | $110.00 | May 11, 4:58 PM |