Work Order 360 View
Detailed work order timeline, KPIs, and analysis
PSM
SLA Clock
Last business day of February 2026 · Target: Feb 27, 2026
✗ SLA Missed (1 biz days late)
🕐 Clock stopped: Canceled (Mar 3, 2026)
▶ Clock Running
Status: Created
Feb 12 → Feb 12, 2026
0 business days (counted)
Running total: 0 of ? biz days used
12d
▶ Clock Running
Status: Ready for Scheduling
Feb 12 → Mar 3, 2026
12 business days (counted)
Running total: 12 of ? biz days used
Created: Feb 12, 2026
Canceled: Mar 3, 2026
Show SLA Clock Detail (2 periods)
| Period |
Status |
Clock |
Biz Days |
Running Total |
| Feb 12 → Feb 12 |
Created |
▶ Running
|
0 |
0 |
| Feb 12 → Mar 3 |
Ready for Scheduling |
▶ Running
|
12 |
12 |
Coordinators
12.7 days
Over SLA
Created: Feb 12, 2026
Due: Apr 30, 2026
Completed: Mar 3, 2026 (58 days early)
⏱️
12.7d in Ready for Scheduling
Longest Stage
🔄
2 transitions
Status Changes
⚠️
11.7d over
Total Delay
📦
0 orders, 0 quotes
Parts & Quotes
AI Analysis
Powered by OpenAI
Generating AI analysis...
🎫
Case #00567699
eBiotrack - Automated New Inspection Created
Closed
Annual Equipment Electrical Safety Test And Calibration Service
Equipment: 39
https://www.ebiotrack.com/inspection.php?iid=33037
🚨
Primary Delay
12.7 days stuck in "Ready for Scheduling"
⏱️
Total Delay
11.7 business days over SLA thresholds
SLA vs Actual Time by Status
Ready for Scheduling
12.7d
/ 1.0d SLA
💬 Activities, Notes & Communications
🔒
Internal CSA Notes
3/3 KHardison, Per Kaylyn, She wants this cancelled per her supervisor.
⚠️
Problem Description
Annual Equipment Electrical Safety Test And Calibration Service
Equipment: 39
https://www.ebiotrack.com/inspection.php?iid=33037
📋
Inbound from +18633482847
Completed
Mar 3, 2026
Per Kaylyn, She wants this cancelled per her supervisor.
📋
Inbound from +18633482847
Completed
Mar 3, 2026
calling to set up appt
Timeline
📞
Case Number:
00567699
Subject:
eBiotrack - Automated New Inspection Created
Status:
Closed
📋
📅
From:
Entered
To:
Ready for Scheduling
Duration in Previous:
0m
🚫
From:
Ready for Scheduling
To:
Canceled
Duration in Previous:
18d 19h
Bottlenecks
Ready for Scheduling
Duration: 12.7 business days (threshold: 1.0 business days)
Exceeded by 11.7 business days