Work Order 360 View
Detailed work order timeline, KPIs, and analysis
PC
SLA Clock
Per client agreement · Target: Nov 26, 2025
✗ SLA Missed (21 biz days late)
🕐 Clock stopped: Canceled (Mar 10, 2026)
▶ Clock Running
Status: Created
Nov 12 → Nov 13, 2025
1 business day (counted)
Running total: 1 of ? biz days used
▶ Clock Running
Status: Scheduled
Nov 13 → Nov 18, 2025
3 business days (counted)
Running total: 4 of ? biz days used
⏸47d
⏸ Clock Paused
Status: Ready for Release
Nov 18 → Jan 29, 2026
47 business days (not counted)
▶ Clock Running
Status: Assigned
Jan 29 → Jan 29, 2026
0 business days (counted)
Running total: 4 of ? biz days used
8d
▶ Clock Running
Status: Scheduled
Jan 29 → Feb 10, 2026
8 business days (counted)
Running total: 12 of ? biz days used
▶ Clock Running
Status: Entered
Feb 10 → Feb 10, 2026
0 business days (counted)
Running total: 12 of ? biz days used
19d
▶ Clock Running
Status: Scheduled
Feb 10 → Mar 10, 2026
19 business days (counted)
Running total: 31 of ? biz days used
▶ Clock Running
Status: Entered
Mar 10 → Mar 10, 2026
0 business days (counted)
Running total: 31 of ? biz days used
Created: Nov 12, 2025
Canceled: Mar 10, 2026
Show SLA Clock Detail (8 periods)
| Period |
Status |
Clock |
Biz Days |
Running Total |
| Nov 12 → Nov 13 |
Created |
▶ Running
|
1 |
1 |
| Nov 13 → Nov 18 |
Scheduled |
▶ Running
|
3 |
4 |
| Nov 18 → Jan 29 |
Ready for Release |
⏸ Paused
|
47 |
—
|
| Jan 29 → Jan 29 |
Assigned |
▶ Running
|
0 |
4 |
| Jan 29 → Feb 10 |
Scheduled |
▶ Running
|
8 |
12 |
| Feb 10 → Feb 10 |
Entered |
▶ Running
|
0 |
12 |
| Feb 10 → Mar 10 |
Scheduled |
▶ Running
|
19 |
31 |
| Mar 10 → Mar 10 |
Entered |
▶ Running
|
0 |
31 |
Dispatch
1.9 days
Over SLA
Holding (excluded from total)
47.6 days
Coordinators
32.6 days
Over SLA
Created: Nov 12, 2025
Due: Nov 26, 2025
Completed: Mar 10, 2026 (103 days late)
⏱️
47.6d in Ready for Release
Longest Stage
🔄
6 transitions
Status Changes
⚠️
28.0d over
Total Delay
📦
0 orders, 0 quotes
Parts & Quotes
AI Analysis
Powered by OpenAI
Generating AI analysis...
🎫
Case #00543263
URGENT Philips WO Request
Closed
FCO86600081: Follow-up Repair to be handled by EMSAR ASP- H29569721CE01
🚨
Primary Delay
47.6 days stuck in "Ready for Release"
⏱️
Total Delay
28.0 business days over SLA thresholds
SLA vs Actual Time by Status
Scheduled
32.6d
/ 2.0d SLA
💬 Activities, Notes & Communications
🔒
Internal CSA Notes
01/29/2026 MNewman - dispatching to Ryan for 2/5 per Fady
01/06/2026 Brod - PO delay extension code , per fady
12/24/2025 EMartin per Fady working with Chad on these repairs will provide resource once completed
12/19/2025 RArnold - Working with Sup for resource
12/08/2025 EMartin sent email to Fady for update on WOs
Quote accepted
11/18/2025 EMartin per Fady working with Chad on these repairs will provide resource once completed
11/13/2025 EMartin dispatching to FSE onsite
⚠️
Problem Description
FCO86600081. Repair to be handled by Philips ASP EMSAR- H29569705BB95
📄
Description
Philips Trilogy EV300 Hospital Ventilator (DS2200X11B / 989805661881)
📞
Call Description
Repair - Trade
Nov 12, 2025 12:00pm
@Deon Malloy EV300 repair - Trade WO-13895316 & WO-13895176
Timeline
📞
Case Number:
00543263
Subject:
URGENT Philips WO Request
Status:
Closed
📋
Work Order:
WO-01314821
Type:
Repair
Priority:
PC
👷
📅
Scheduled For:
2025-11-14T05:00:00.000+0000, 2025-11-14T00:00:00.000+0000, 2025-11-14T13:00:00.000+0000
🗓️
From:
Entered
To:
Scheduled
Duration in Previous:
21h 49m
👷
📅
Scheduled For:
2025-11-13T13:00:00.000+0000
✅
From:
Scheduled
To:
Ready for Release
Duration in Previous:
5d 4h
👷
👷
From:
Ready for Release, Assigned
To:
Assigned, Scheduled
Duration in Previous:
71d 19h, 0m
📅
Scheduled For:
2026-02-05T13:00:00.000+0000
🆕
📅
Scheduled For:
2026-02-13T00:00:00.000+0000, 2026-02-13T06:00:00.000+0000
🗓️
From:
Entered
To:
Scheduled
Duration in Previous:
2m
📅
Scheduled For:
2026-02-13T14:00:00.000+0000
🆕
From:
Scheduled, Entered
To:
Entered, Canceled
Duration in Previous:
28d 0h, 0m
Bottlenecks
Entered
Duration: 1.9 business days (threshold: 4.0 business hours)
Exceeded by 1.4 business days
Scheduled
Duration: 4.0 business days (threshold: 2.0 business days)
Exceeded by 2.0 business days
Scheduled
Duration: 9.0 business days (threshold: 2.0 business days)
Exceeded by 7.0 business days
Scheduled
Duration: 19.6 business days (threshold: 2.0 business days)
Exceeded by 17.6 business days